
 |
 |
 |

 |
U.S. Nuclear Regulatory
Commission |
 | |
 |
 |
Availability
Notice
Table of Contents - Volume 1
Publication Information
[ Next
| Table
of Contents ]
Final Report
Manuscript Completed: April 1996
Date Published: May 1996
Division of Regulatory Applications
Office of Nuclear Regulatory
Research
U.S. Nuclear Regulatory Commission
Washington, DC
20555-0001
Abstract
[ Prev
| Next
| Table
of Contents ]
The Nuclear Regulatory Commission (NRC) anticipates that it will receive
applications for renewal of the operating licenses of a significant portion of
existing nuclear power plants. This Generic Environmental Impact Statement
(GEIS) examines the possible environmental impacts that could occur as a result
of renewing licenses of individual nuclear power plants under 10 CFR Part 54.
The GEIS, to the extent possible, establishes the bounds and significance of
these potential impacts. The analyses in the GEIS encompass all operating
light-water power reactors. For each type of environmental impact the GEIS
attempts to establish generic findings covering as many plants as possible.
While plant and site-specific information is used in developing the generic
findings, the NRC does not intend for the GEIS to be a compilation of individual
plant environmental impact statements.
This GEIS has three principal objectives: (1) to provide an understanding of
the types and severity of environmental impacts that may occur as a result of
license renewal of nuclear power plants under 10 CFR Part 54, (2) to identify
and assess those impacts that are expected to be generic to license renewal, and
(3) to support a rulemaking (10 CFR Part 51) to define the number and scope
of issues that need to be addressed by the applicants in plant-by-plant license
renewal proceedings. To accomplish these objectives, the GEIS makes maximum use
of environmental and safety documentation from original licensing proceedings
and information from state and federal regulatory agencies, the nuclear utility
industry, the open literature, and professional contacts.
Figures
[ Prev
| Next
| Table
of Contents ]
Figure
2.1 Pressurized-water-reactor power generation system
Figure
2.2 Boiling-water-reactor generating system
Figure
2.3 License renewal schedule and outage periods considered for environmental
impact initiator definition
Figure
3.1 The seven case study nuclear plants
Figure
4.1 Examples of typical transmission line towers
Figure
5.1 Potential exposure pathways to individuals
Figure
5.2 Log plot of early fatalities (average deaths per reactor-year) for final
environmental statement boiling-water reactor plants, fitted regression line
(solid curve), and 95 percent normal-theory upper prediction confidence bounds
(dotted curve)
Figure
5.3 Log plot of early fatalities (average deaths per reactor-year) for final
environmental statement pressurized-water reactor plants, fitted regression line
(solid curve), and 95 percent normal-theory upper prediction confidence bounds
(dotted curve)
Figure
5.4 Log plot of normalized latent fatalities (average deaths per 1000 MW
reactor-year) for final environmental statement boiling-water reactor plants,
fitted regression line (solid curve), and 95 percent distribution-free upper
prediction confidence bounds (dotted curve)
Figure
5.5 Log plot of normalized latent fatalities (average deaths per 1000 MW
reactor-year) for final environmental statement pressurized-water reactor
plants, fitted regression line (solid curve), and 95 percent distribution-free
upper prediction confidence bounds (dotted curve)
Figure
5.6 Log plot of normalized total dose (person-rem per 1000 MW reactor-year) for
final environmental statement boiling-water reactor plants, fitted regression
line (solid curve), and 95 percent distribution-free upper prediction confidence
bounds (dotted curve)
Figure
5.7 Log plot of normalized total dose (person-rem per 1000 MW reactor-year) for
final environmental statement pressurized-water reactor plants, fitted
regression line (solid curve), and 95 percent distribution-free upper prediction
confidence bounds (dotted curve)
Figure
5.8 Water body surface areas and volumes within 80 km (50 miles) of
representative nuclear power plant sites (potentially affected water bodies)
Figure
5.9 Water body surface areas and volumes within 80 km (50 miles) of the reactor
site and within six of the 22.50 compass sectors that exhibit the greatest
percentage of time for which the wind blows toward that compass direction
(likely affected water bodies)
Figure
5.10 Water body flow rate at representative nuclear power plant sites
Figure
5.11 Contaminant residence time (flushing rate) and surface area-volume ratios
for water bodies within an 80-km (50-mile) radius of selected nuclear power
plants
Figure
6. 1 Low-level radioactive waste compact status
Figure
7.1 Typical pressurized-water reactor generating station layout
Figure
7.2 Site layout on a typical boiling-water reactor power plant
Figure
7.3 Buildup of activation products in pressurized-water reactor internal
components as a function of effective full-power years
Figure
7.4 Time dependence of radioactivity and dose rate in a boiling-water reactor
core shroud after 40 years of operation
Figure
8.1 U.S. wind energy resources
Figure
8.2 Solar resource availability: annual average daily direct normal solar
radiation
Figure
8.3 U.S. conventional hydroelectric generating capacity, developed and
undeveloped
Figure
8.4 U.S. known and potential geothermal energy resources
Acronyms and Abbreviations
[ Prev
| Next
| Table
of Contents ]
ADS |
automatic depressurization system |
AEA |
Atomic Energy Act of 1954 |
AEC |
U.S. Atomic Energy Commission |
AEO |
Atomic Energy Outlook 1990 |
AFUDC |
allowance for funds used during construction |
AGA |
American Gas Association |
AGR |
advanced gas-cooled reactor |
AIRFA |
American Indian Religious Freedom Act |
ALARA |
as low as reasonably achievable |
ALI |
annual limits on intake |
A/m |
amps per meter |
AML |
acute myelogenous leukemia |
ANO |
Arkansas Nuclear One |
ANOVA |
analysis of variance |
ANSI |
American National Standards Institute |
AP&L |
Arkansas Power and Light |
ASME |
American Society of Mechanical Engineers |
ATWS |
anticipated transit without scram |
|
|
BAU |
business-as-usual |
BEIR |
Biological Effects of Ionizing Radiation |
BIG/GT |
biomass-gasifier/gas turbine |
BRC |
below regulatory concern |
BSD |
Burlington School District |
B&W |
Babcock and Wilcox |
BWR |
boiling-water reactor |
|
|
° C |
degrees centigrade (Celsius) |
CAA |
Clean Air Act |
CAAA |
Clean Air Act Amendments of 1990 |
CCC |
California Coastal Commission |
CDE |
committed dose equivalent |
CDF |
core damage frequencies |
CE |
Combustion Engineering |
CEDE |
committed effective dose equivalent |
CEQ |
Council on Environmental Quality |
CERCLA |
Comprehensive Environmental Response, Compensation, and Liability
Act |
CFC |
chlorofluorocarbon |
CFR |
Code of Federal Regulations |
Ci |
curie |
CML |
chronic myelogenous leukemia |
CMSA |
consolidated metropolitan statistical area |
CNS |
central nervous system |
CO |
carbon monoxide |
ConEd |
Consolidated Edison |
CPI |
containment performance improvement |
CPW |
continuous polymer wire |
CRAC |
Consequence (of) Reactor Accident Code |
CRD |
control rod drive |
CWA |
Clean Water Act of 1977 |
CZMA |
Coastal Zone Management Act |
|
|
DAC |
derived air concentrations |
DAW |
dry active waste |
DE |
dose equivalent |
DECON |
a nuclear plant decommissioning method |
DER |
Florida Department of Environmental Regulation |
DFA |
direct fluorescent antibody |
DMBA |
dimethylbenzanthracene |
DNR |
Florida Department of Natural Resources |
DO |
dissolved oxygen |
DOE |
U.S. Department of Energy |
DOI |
Department of Interior |
DRBC |
Delaware River Basin Commission |
DREF |
dose rate effectiveness factor |
DRI |
Data Resources Incorporated |
DSC |
dry shielded canister |
DSM |
demand-side management |
|
|
E |
electric field |
EA |
environmental assessment |
EAB |
exclusion area boundary |
EDE |
effective dose equivalent |
EEC |
European Economic Community |
EEDB |
Energy Economic Data Base |
EEG |
electroencephalogram |
EEI |
Edison Electric Institute |
E-field |
electric-field |
EI |
exposure index |
EIA |
Energy Information Administration |
EIS |
environmental impact statement |
EKG |
electrocardiogram |
ELF |
extremely low frequency |
EM |
electromagnetic |
EMF |
electromagnetic field |
ENTOMB |
a nuclear plant decommissioning method |
EO |
Executive Order |
EPA |
U.S. Environmental Protection Agency |
EPACT |
Energy Policy Act of 1992 |
EPCRA |
Emergency Planning and and Community Right-to-Know Act |
EPRI |
Electric Power Research Institute |
EPZ |
emergency planning zone |
ESA |
Endangered Species Act |
ESEERCO |
Empire State Electric Energy Research Corporation |
|
|
FDA |
U.S. Food and Drug Administration |
FEMA |
U.S. Federal Emergency Management Agency |
FERC |
Federal Energy Regulatory Commission |
FES |
final environmental statement |
FFCA |
Federal Facilities Compliance Agreement |
FIFRA |
Federal Insecticide, Fungicide, and Rodenticide Act |
FIS |
federal interim storage |
FONSI |
finding of low significant impact |
FPC |
Florida Power Commission |
FP&L |
Florida Power & Light |
FR |
Federal Register |
FSAR |
final safety analysis report |
FWCA |
Fish and Wildlife Coordination Act |
FWS |
U.S. Fish and Wildlife Service |
|
|
GBD |
gas bubble disease |
GCHWR |
gas-cooled heavy-water-moderated reactor |
GCR |
gas-cooled reactor |
GE |
General Electric Company |
GEIS |
generic environmental impact statement |
g/m2/s |
gallons per square meter per second |
GNP |
gross national product |
GNSI |
General Nuclear Systems, Inc. |
GPU |
General Public Utilities Corporation |
GRI |
Gas Research Institute |
GTCC |
greater-than-class-C |
GW |
gigawatt |
GWd |
gigawatt-days |
|
|
HC |
hydrocarbons |
HL&P |
Houston Lighting and Power Company |
HLW |
high-level radioactive waste |
HP |
health physics |
HPOF |
high-pressure oil-filled |
HRS |
hazard ranking system |
HSM |
horizontal storage module |
HSWA |
Hazardous and Solid Waste Amendments of 1984 |
HWR |
heavy-water reactor |
|
|
ICRP |
International Commission on Radiological Protection |
IGSCC |
intergranular stress-cracking corrosion |
IMP |
intramembranous protein particle |
INIRC |
International Non-Ionizing Radiation Protection Association |
INPO |
Institute of Nuclear Power Operations |
IOR |
ion exchange resin |
IPA |
integrated plant assessment |
IPE |
individual plant examination |
IRPA |
International Radiation Protection Association |
ISFSI |
independent spent-fuel storage installation |
ISI |
in-service inspection |
ISTM |
inspection, surveillance, testing, and maintenance |
|
|
kV |
kilovolt |
kV/m |
kilovolts per meter |
kW |
kilowatt |
kWh |
kilowatt-hour |
|
|
LD |
Legionnaires' disease |
LDR |
land disposal restrictions |
LDSD |
Lower Dauphin School District |
LET |
linear energy transfer |
LLRWPAA |
Low-Level Radioactive Waste Policy Amendments Act of 1985 |
LLW |
low-level radioactive waste |
LMFBR |
liquid-metal first breeder reactor |
LOCA |
loss-of-coolant accident |
LOS |
level of service |
LPGS |
Liquid Pathway Generic Study |
LPZ |
low population zone |
LWR |
light-water reactor |
|
|
m |
meter |
mA |
milliamperes |
MACCS |
MELCOR Accident Consequence Code System |
MANOVA |
multivariate analyses of covariance |
MAP |
Methodologies Applications Program |
MASD |
Middletown Area School District |
mCi |
milliCurie |
MCLG |
maximum contaminant goal levels |
MDNR |
Maryland Department of Natural Resources |
MFD |
magnetic flux density |
mG |
milligauss |
mM |
millimole |
MMPA |
Marine Mammals Protection Act |
MPC |
maximum permissible concentration |
MPRSA |
Marine Protection, Research, and Sanctuaries Act |
MPOB |
maximum permissible organ burden |
MRC |
Marine Review Committee |
mrem |
millirem |
MRS |
monitored retrievable storage |
m3/s |
cubic meters per second |
MSA |
metropolitan statistical area |
MSW |
municipal solid waste |
mT |
millitesla |
MTIHM |
metric tons of initial heavy metal |
MTU |
metric tons of uranium |
mV/m |
millivolts per meter |
MW |
megawatt |
MWd |
megawatt-days |
MW(e) |
megawatt (electrical) |
MW(t) |
megawatt (thermal) |
MYL |
middle year of license |
MYR |
middle year of relicense |
m g/g |
micrograms per gram |
m m |
micron |
|
|
NAA |
nonattainment area |
NAAQS |
National Ambient Air Quality Standards |
NAS |
National Academy of Sciences |
NBS |
National Bureau of Standards (now NIST) |
NCA |
National Coal Association |
NCRP |
National Council on Radiation Protection and Measurements |
NEC |
normalized expected cost |
NEPA |
National Environmental Policy Act of 1969 |
NERC |
North American Electric Reliability Council |
NESC |
National Electric Safety Code |
NESHAP |
National Emission Standards for Hazardous Air Pollutants |
NGS |
nuclear generating station |
NHPA |
National Historic Preservation Act of 1966 |
NIEHS |
National Institute of Environmental Health Sciences |
NIOSH |
National Institute for Occupational Safety and Health |
NIST |
National Institute of Standards and Technology |
NLF |
normalized latent facility |
NMFS |
National Marine Fisheries Service |
NMR |
nuclear magnetic resonance |
NOx |
nitrogen oxide(s) |
NPA |
National Planning Association |
NPDES |
National Pollutant Discharge Elimination System |
NPP |
nuclear power plant |
NRC |
U.S. Nuclear Regulatory Commission |
NSPS |
new source performance standards |
NSSS |
nuclear steam supply system |
NTD |
normalized total dose |
NUHOMS |
Nutech Horizontal Modular System |
NUMARC |
Nuclear Utilities Management and Resources Council |
NUREG |
an NRC reports category |
NUS |
NUS Corporation |
NWPA |
Nuclear Waste Policy Act of 1982 |
NYSDEC |
New York State Department of Environmental Conservation |
|
|
ODC |
ornithine decarboxylase |
OHMS |
hydroxy melatonin sulfate |
OL |
operating license |
O&M |
operation and maintenance |
ONS |
Oconee Nuclear Station |
OPEC |
Organization of Petroleum Exporting Countries |
OR |
odds ratio |
ORNL |
Oak Ridge National Laboratory |
OSHA |
Occupational Safety and Health Administration |
OTA |
Office of Technology Assessment |
OTEC |
ocean thermal energy conversion |
|
|
PAME |
primary amoebic meningoencephalitis |
PASNY |
Power Authority for the State of New York |
PCB |
polychlorinated biphenyl |
PG&E |
Pacific Gas and Electric |
pH |
hydrogen-ion concentration |
PHWR |
pressurized heavy-water reactor |
PLEX |
plant life extension |
PM |
particulate matter |
PMR |
proportionate mortality ratios |
ppm |
parts per million |
PSD |
prevention of significant deterioration |
PRA |
probabilistic risk assessment |
PTH |
parathyroid hormone |
PURPA |
Public Utility Regulatory Policies Act of 1978 |
PURTA |
Public Utilities Realty Tax Assessment of 1970 |
PV |
solar photovoltaic |
PWR |
pressurized-water reactor |
|
|
QA |
quality assurance |
|
|
RBE |
relative biological effectiveness |
RCB |
reactor containment building |
RCRA |
Resource Conservation and Recovery Act of 1976 |
RD&D |
1. research, design, and development |
|
2. research, development, and demonstration |
RERF |
Radiation Effects Research Council |
RET |
renewable energy technology |
RF |
radio frequency |
RHR |
residual heat removal |
RIMS |
Regional Industrial Multiplier System |
rms |
root mean square |
ROW |
right(s) of way |
RPV |
reactor pressure vessel |
RRY |
reference reactor year |
RSD |
Russellville (Ark.) School District |
RSS |
Reactor Safety Study |
RV |
recreational vehicle |
RY |
reactor-year |
|
|
SAFSTOR |
a nuclear plant decommissioning method |
SAMDA |
severe accident mitigation design alternative |
SAND |
Data Resource Incorporated's detailed electricity sector model |
SAND NUPLEX |
SAND generating capacity projections |
SAR |
safety analysis report |
SARA |
Superfund Amendments and Reauthorization Act |
SCE |
Southern California Edison |
SCM |
Surface Compartment Model |
SDG&E |
San Diego Gas & Electric Company |
SDWA |
Safe Drinking Water Act |
SEA |
Science and Engineering Associates, Inc. |
SER |
safety evaluation report |
SERI |
Solar Energy Research Institute |
SEV |
state equalized value |
SF |
spent fuel |
SHPO |
state historic preservation office |
SI |
International System |
SIR |
standardized incidence ratio |
SLB |
shallow land burial |
SMR |
standardized mortality ratio |
SMITTR |
surveillance, on-line monitoring, inspections, testing, trending, and
recordkeeping |
SMSA |
standard metropolitan statistical area |
SO2 |
sulfur dioxide |
SOK |
San Onofre kelp bed |
SONGS |
San Onofre Nuclear Generating Station |
SRBC |
Susquehanna River Basin Commission |
SSC |
systems, structures, and components |
|
|
t |
metric tons |
TDE |
total dose equivalent |
TDS |
total dissolved solids |
TEDE |
total effective dose equivalent |
TMI |
Three Mile Island (nuclear plant) |
TRU |
transuranic |
TSCA |
Toxic Substances Control Act |
TVA |
Tennessee Valley Authority |
|
|
UCB |
upper confidence bound |
UFC |
uranium fuel cycle |
UHV |
ultra-high voltage |
UNSCEAR |
United Nations Scientific Committee on the Effects of Atomic
Radiation |
USD |
Unified School District |
USGS |
U.S. Geological Survey |
USI |
unresolved safety issue |
|
|
VDT |
video display terminal |
VR |
volume reduction |
VRF |
volume reduction factor |
|
|
W |
watt |
WCGS |
Wolf Creek Generating Station |
WHO |
World Health Organization |
WNP-2 |
Washington Nuclear Project |
WTE® |
Whole Tree Energy® |
Executive Summary
[ Prev
| Next
| Table
of Contents ]
This Generic Environmental Impact Statement (GEIS) for license renewal of
nuclear power plants was undertaken to
(1) assess the environmental impacts that could be associated with nuclear
power plant license renewal and an additional 20 years of operation of
individual plants and
(2) provide the technical basis for an amendment to the Nuclear Regulatory
Commission's (NRC's) regulations, 10 CFR Part 51, "Environmental
Protection Regulations for Domestic Licensing and Related Regulatory Functions,"
with regard to the renewal of nuclear power plant operating licenses. The rule
amendment and this document were initiated to enhance the efficiency of the
license renewal process by documenting in this GEIS and codifying in the
Commission's regulations the environmental impacts that are well understood.
Under NRC's environmental protection regulations in 10 CFR Part 51, renewal
of a nuclear power plant operating license is identified as a major federal
action significantly affecting the quality of the human environment, and thus an
environmental impact statement (EIS) is required for a plant license renewal
review. The EIS requirements for a plant-specific license renewal review are
specified in 10 CFR Part 51. Operating licenses may be renewed for up to 20
years beyond the 40-year term of the initial license. License renewal applicants
perform evaluations and assessments of their facility to provide sufficient
information for the NRC to determine whether continued operation of the facility
during the renewal term will endanger public health and safety or the
environment. The assessments also help to determine what activities and
modifications are necessary at the time of license renewal and throughout the
renewal term to ensure continued safe operation of the plant. Most utilities are
expected to begin preparation for license renewal about 10 to 20 years before
expiration of their original operating licenses. For the analysis in this GEIS,
the staff anticipates that plant refurbishment undertaken specifically for
license renewal would probably be completed during normal plant outage cycles,
beginning 8 years before the original license expires, and during one longer
outage, if a major refurbishment item is involved.
The Commission will act on an application for license renewal submitted by a
licensee of an operating nuclear power plant. Although a licensee must have a
renewed license to operate a plant beyond the term of the existing operating
license, the possession of that license is just one of a number of conditions
that must be met for the licensee to continue plant operation during the term of
the renewed license. If the Commission grants a license renewal for a plant,
state regulatory agencies and the owners of the plant would ultimately decide
whether the plant will continue to operate based on factors such as need for
power or other matters within the state's jurisdiction or the purview of the
owners. Economic considerations will play a primary role in the decision made by
state regulatory agencies and the owners of the plant. Thus, for license renewal
reviews, the Commission has adopted the following definition of purpose and
need:
- The purpose and need for the proposed action (renewal of an operating
license) is to provide an option that allows for power generation capability
beyond the term of a current nuclear power plant operating license to meet
future system generating needs, as such needs may be determined by State,
utility, and, where authorized, Federal (other than NRC) decisionmakers.
In Chapter 8, the Commission considers the environmental consequences of the
no-action alternative (i.e., denying a license renewal application) and the
environmental consequences of the various alternatives for replacing lost
generating capacity that would be available to a utility and other responsible
energy planners. No conclusions are made in this document about the relative
environmental consequences of license renewal or the construction and operation
of alternative facilities for generating electric energy. The information in the
GEIS is available for use by the NRC and the licensee in performing the
site-specific analysis of alternatives. This information will be updated
periodically, as appropriate.
The GEIS summarizes the findings of a systematic inquiry into the potential
environmental consequences of renewing the licenses of and operating individual
nuclear power plants for an additional 20 years. The inquiry identifies the
attributes of the nuclear power plants, such as major features and plant
systems, and the ways the plants can affect the environment. The inquiry also
identifies the possible refurbishment activities and modifications to
maintenance and operating procedures that might be undertaken given the
requirements of the safety review as provided for in the Commission's
regulations in 10 CFR Part 54, or given a utility's motivation to increase
economic efficiency. Two scenarios were developed to identify possible
initiators of environmental impacts from the possible set of refurbishment
activities and continuation of plant operation during the renewal term. One
scenario was developed as a typical but somewhat conservative scenario for
license renewal, intended to be representative of the type of program that many
licensees seeking license renewal might implement. The other scenario is highly
conservative, encompassing considerably more activities, and is intended to
characterize a reasonable upper bound of impact initiators that might result
from license renewal.
The general analytical approach to each environmental issue is to
(1) describe the activity that affects the environment, (2) identify
the population or resource that is affected, (3) assess the nature and
magnitude of the impact on the affected population or resource,
(4) characterize the significance of the effect for both beneficial and
adverse effects, (5) determine whether the results of the analysis apply to all
plants, and (6) consider whether additional mitigation measures would be
warranted for impacts that would have the same significance level for all
plants.
A standard of significance was established for assessing environmental
issues; and, because significance and severity of an impact can vary with the
setting of a proposed action, both "context" and "intensity" as defined in the
Council on Environmental Quality regulations (40 CFR 1508.27) were
considered. With these standards as a basis, each impact was assigned to one of
three significance levels:
Small: For the issue, environmental effects are not
detectable or are so minor that they will neither destabilize nor noticeably
alter any important attribute of the resource. For the purposes of assessing
radiological impacts, the Commission has concluded that those impacts that do
not exceed permissible levels in the Commission's regulations are considered
small.
Moderate: For the issue, environmental effects are
sufficient to alter noticeably but not to destabilize important attributes of
the resource.
Large: For the issue, environmental effects are clearly
noticeable and are sufficient to destabilize important attributes of the
resource.
The discussion of each environmental issue in the GEIS includes an
explanation of how the significance category was determined. For issues in which
probability of occurrence is a key consideration (i.e., accident consequences),
the probability of occurrence is factored into the determination of
significance. In determining the significance levels, it is assumed that ongoing
mitigation measures would continue and that mitigation measures employed during
plant construction would be employed during refurbishment, as appropriate. The
potential benefits of additional mitigation measures are not considered in
determining significance levels.
In addition to determining the significance of environmental impacts
associated with an issue for that issue, a determination was made whether the
analysis in the GEIS could be applied to all plants and whether additional
mitigation measures would be warranted. The categories to which an issue may be
assigned follow.
|
Category 1: For the issue, the analysis reported in the GEIS
has shown the following: |
|
(1) |
the environmental impacts associated with the issue have been
determined to apply either to all plants or, for some issues, to plants
having a specific type of cooling system or other specified plant or site
characteristics; |
|
(2) |
a single significance level (i.e., small, moderate, or large) has been
assigned to the impacts (except for collective off-site radiological
impacts from the fuel cycle and from high-level-waste and spent-fuel
disposal); and |
|
(3) |
mitigation of adverse impacts associated with the issue has been
considered in the analysis, and it has been determined that additional
plant-specific mitigation measures are likely not to be sufficiently
beneficial to warrant implementation. |
|
Category 2: For the issue, the analysis reported in the GEIS
has shown that one or more of the criteria of Category 1 cannot be
met, and therefore, additional plant-specific review is
required. |
This final GEIS assesses 92 environmental issues. Sixty-eight of these issues
are found to be Category 1 and are identified in 10 CFR Part 51 as not
requiring additional plant-specific analysis. Guidance on the analyses required
for each of the other 24 issues is provided in 10 CFR Part 51. A summary of the
findings for the 92 environmental issues is provided in Table 9.1 of this
GEIS and summarized in narrative below.
Impacts of Refurbishment
[ Prev
| Next
| Table
of Contents ]
- On-site land use impacts are expected to be of small significance at all
sites. Temporary disturbance of land may be mitigated by restoration to its
original condition after refurbishment. This is a Category 1 issue.
- Nuclear power plant atmospheric emissions would either remain constant
during refurbishment or decrease if the plant were partially or totally shut
down. Small quantities of fugitive dust and gaseous exhaust emissions from
motorized equipment operation during construction and refurbishment would
temporarily increase ambient concentrations of particulate matter and gaseous
pollutants in the vicinity of the activity but would not be expected to
measurably affect ambient concentrations of regulated pollutants off-site.
Additional exhaust emissions from the vehicles of up to 2300 personnel could
be cause for some concern in geographical areas of poor or marginal air
quality, but a general conclusion about the significance of the potential
impact cannot be drawn without considering the compliance status of each site
and the numbers of workers to be employed during the outage. This is a
Category 2 issue.
- Proven erosion control measures such as best management practices are
expected to be implemented at all plants and to minimize impacts to local
water quality from runoff in disturbed areas. Consequently, impacts of
refurbishment on surface water quality are expected to be of small
significance at all plants. Because the effects of refurbishment are
considered to be of small significance and potential mitigation measures are
likely to be costly, the staff does not consider implementation of mitigation
measures beyond best management practices to be warranted. This is a
Category 1 issue.
- Additional water requirements during construction and refurbishment would
be a small fraction of cooling water requirements of the operating power
plant. If the plant were partially or totally shut down, cooling water use
would decline. Water use during refurbishment is expected to have impacts of
small significance on the local water supply. The only potential mitigation
for any increase in water consumption would be to acquire the additional water
from some other source. However, because this approach would provide very
little, if any, environmental benefit and would be costly, the staff does not
consider implementation of additional mitigation to be warranted. This is a
Category 1 issue.
- Deep excavations and site dewatering would not be required during
refurbishment. Consequently, the impacts of refurbishment on groundwater would
be of small significance at all sites. No additional mitigation measures would
be warranted because there would be no adverse impacts to mitigate. This is a
Category 1 issue.
- Effluent discharges from the cooling system of a nuclear power plant would
either remain constant during refurbishment or decrease if the plant were
partially or totally shut down. Effects of changes in water withdrawals and
discharges during refurbishment would be of small significance. No additional
mitigation measures beyond those implemented during the current license term
would be warranted because there would be no adverse impacts to mitigate. This
is a Category 1 issue.
- The small on-site change in land use associated with refurbishment and
construction could disturb or eliminate a small area of terrestrial habitat
[up to 4 ha (10 acres)]. The significance of the loss of habitat depends on
the importance of the plant or animal species that are displaced and on the
availability of nearby replacement habitat. Impacts would be potentially
significant only if they involved wetlands, staging or resting areas for large
numbers of waterfowl, rookeries, restricted wintering areas for wildlife,
communal roost sites, strutting or breeding grounds for gallinaceous birds, or
rare plant community types. Because ecological impacts cannot be determined
without considering site- and project-specific details, the potential
significance of those impacts cannot be determined generically. This is a
Category 2 issue.
- Because of refurbishment-related population increases, impacts on housing
could be of moderate or large significance at sites located in rural and
remote areas, at sites located in areas that have experienced extremely slow
population growth (and thus slow or no growth in housing), or where growth
control measures that limit housing development are in existence or have
recently been lifted. This is a Category 2 issue.
- Tax impacts, which involve small to moderate increases in the direct and
indirect tax revenues paid to local jurisdictions, are considered beneficial
in all cases.
- In the area of public services, in-migrating workers could induce impacts
of small to large significance to education, with the larger impacts expected
to occur in sparsely populated areas. Impacts of small to moderate
significance may occur to public utilities at some sites. Transportation
impacts could be of large significance at some sites. These socioeconomic
issues are Category 2.
- The impacts of refurbishment on other public services (public safety,
social services, and tourism and recreation) are expected to be of small
significance at all sites. No additional mitigation measures beyond those
implemented during the current license term would be warranted because
mitigation would be costly and the benefits would be small. These are
Category 1 issues.
- In-migrating workers could induce impacts of small to moderate
significance to off-site land use. The larger impacts are expected to occur in
sparsely populated areas. This is a Category 2 issue.
- Based on the findings at the case study sites, refurbishment-related
economic effects would range from small benefits to moderate benefits at all
nuclear power plant sites. No adverse effects to economic structure would
result from refurbishment-related employment.
- Site-specific identification of historic and archaeological resources and
determination of impacts to them must occur during the consultation process
with the State Historic Preservation Office (SHPO) as mandated by the National
Historic Preservation Act. Impacts to historic resources could be large if the
SHPO determines that significant historic resources would be disturbed or
their historic character would be altered by plant refurbishment activities.
The significance of potential impacts to historic and archaeological resources
cannot be determined generically. This is a Category 2 issue.
- The impact on aesthetic resources is found to be of small significance at
all sites. Because there will be no readily noticeable visual intrusion,
consideration of mitigation is not warranted. This is a Category 1 issue.
- Radiation impacts to members of the public are considered to be of small
significance because public exposures are within regulatory limits. Also, the
estimated cancer risk to the average member of the public is much less than 1
x 10-6. Because current mitigation practices have resulted in
declining public radiation doses for nearly two decades, additional mitigation
is not warranted. The impact on human health is a Category 1 issue.
- Occupational radiation exposure during refurbishment meets the ard of
small significance. Because the as-low-as-reasonably-achievable (ALARA)
program continues to reduce occupational doses, no additional mitigation
program is warranted. This is a Category 1 issue.
- The significance of potential impacts to threatened and endangered species
cannot be determined generically because compliance with the Endangered
Species Act cannot be assessed without site-specific consideration of
potential effects on threatened and endangered species. This is a
Category 2 issue.
Impacts of Operation
[ Prev
| Next
| Table
of Contents ]
- It is not possible to reach a conclusion about the significance of
potential impacts to threatened and endangered species at this time because
(1) the significance of impacts on such species cannot be assessed
without site- and project-specific information that will not be available
until the time of license renewal and (2) additional species that are
threatened with extinction and that may be adversely affected by plant
operations may be identified between the present and the time of license
renewal. This is a Category 2 issue.
- The staff examined nine aspects of water quality that might be affected by
power plant operations: current patterns at intake and discharge structures,
salinity gradients, temperature effects on sediment transport, altered thermal
stratification of lakes, scouring from discharged cooling water,
eutrophication, discharge of biocides, discharge of other chemical
contaminants (e.g., metals), and discharge of sanitary wastes. Open-cycle
cooling systems are more likely than other cooling systems to have such
effects because they withdraw and discharge very large volumes of water;
however, the impacts for each of these effects were found to be of small
significance for all plants, regardless of cooling system type. For each type
of impact, the staff considered potential mitigation measures but found that
none were warranted because they would be costly and would have very small
environmental benefits. These are Category 1 issues.
- The staff found no potential for water use conflicts or riparian plant and
animal community impacts of moderate or large significance for plants with
open-cycle cooling systems because they are used on large water bodies.
Because the potential mitigation measures are costly and because the potential
benefits are small, the staff does not consider mitigation to be warranted.
These are Category 1 issues.
- The staff found that water use conflicts and the effects of consumptive
water use on in-stream aquatic and riparian terrestrial communities could be
of moderate significance at some plants that employ cooling-tower or
cooling-pond systems because they are often located near smaller water bodies.
For plants with these cooling systems, these are Category 2 issues.
- The staff examined 12 potential effects that nuclear power plant cooling
systems may have on aquatic ecology: (1) impingement of fish;
(2) entrainment of fish (early life stages); (3) entrainment of
phytoplankton and zooplankton; (4) thermal discharge effects;
(5) cold shock; (6) thermal plume barriers to migrating fish;
(7) premature emergence of aquatic insects; (8) stimulation of
nuisance organisms; (9) losses from predation, parasitism, and disease
among organisms exposed to sublethal stresses; (10) gas supersaturation;
(11) low dissolved oxygen in the discharge; and (12) accumulation of
contaminants in sediments or biota. Except for three potential impacts
(entrainment of fish and shellfish, impingement of fish and shellfish, and
thermal discharge effects), each of these was found to be of small
significance at all plants. Because mitigation would be costly and provide
little environmental benefit, no additional mitigation measures beyond those
implemented during the current license term are warranted. These are
Category 1 issues. The other three impacts would be of small significance
at all plants employing cooling-tower cooling systems. Because mitigation
would be costly and provide little environmental benefit, no additional
mitigation measures beyond those implemented during the current license term
are warranted. For those plants, these are Category 1 issues. However,
the impacts may be of greater significance at some plants employing open-cycle
or cooling-pond systems; and these are Category 2 issues for those
plants.
- The staff found that groundwater use of less than 0.0063 m3/s
(100 gal/min) is of small significance because the cone of depression will not
extend beyond the site boundary. Conflicts might result from several types of
groundwater use by nuclear power plants. If groundwater conflicts arose, they
could be resolvable by deepening the affected wells, but no such mitigation is
warranted because sites producing less than 0.0063 m3/s (100
gal/min) would not have a cone of depression that extends beyond the site
boundary. This is a Category 1 issue. Plants that extract more than
0.0063 m3/s (100 gal/min), including plants using Ranney
wells, may have groundwater use conflicts of moderate or large significance.
Groundwater use is a Category 2 issue for such plants.
- Cooling system makeup water consumption may cause groundwater use
conflicts. During times of low flow, surface water withdrawals for cooling
tower makeup from small rivers can reduce groundwater recharge. Because the
significance of such impacts cannot be determined generically, this is a
Category 2 issue.
- Groundwater withdrawals could cause adverse effects on groundwater quality
by inducing intrusion of lower-quality groundwater into the aquifer. The staff
found that the significance of these potential impacts is of small
significance in all cases. Because all plants except Grand Gulf use relatively
small quantities of groundwaters and surface water intrusion at Grand Gulf
would not preclude current water uses, the staff found that mitigation was not
warranted. This is a Category 1 issue.
- Cooling ponds leak an undetermined quantity of water through the pond
bottom. Because the water in cooling ponds is elevated in salts and metals,
such leakage may contaminate groundwater. The staff found that groundwater
quality impacts of ponds that are located in salt marshes would be of small
significance in all cases because salt marshes already have poor water
quality. This is a Category 1 issue. Cooling ponds that are not located in
salt marshes may have groundwater quality impacts of small, moderate, or large
significance. This is a Category 2 issue.
- Small amounts of ozone and substantially smaller amounts of oxides of
nitrogen are produced by transmission lines; however, ozone concentrations
generated by transmission lines are too low to cause any significant effects.
The minute amounts of oxides of nitrogen produced are also insignificant.
Thus, air quality impacts associated with the operational transmission lines
during the renewal term are expected to be of small significance at all sites.
Potential mitigation measures would be very costly and are not warranted. This
is a Category 1 issue.
- The potential impact of cooling tower drift on crops and ornamental
vegetation arising from operations during the license renewal term is expected
to be of small significance for all nuclear plants. No mitigation measures
beyond those implemented during the current license term are warranted because
there have been no measurable effects on crops or ornamental vegetation from
cooling tower drift. This is a Category 1 issue.
- The impact of cooling towers on natural plant communities should continue
not to result in measurable degradation as a result of license renewal and
will therefore be of small significance. Because the impacts of cooling tower
drift on native plants are expected to be small and because potential
mitigation measures would be costly, no mitigation measures beyond those
during the current term license would be warranted. This is a Category 1
issue.
- Bird mortality from collision with power lines associated with nuclear
plants is of small significance for all plants because bird mortality is
expected to remain a small fraction of total collision mortality associated
with all types of man-made objects. Because the numbers of birds killed from
collision with cooling towers are not large enough to affect local population
stability or species function within the ecosystem, consideration of further
mitigation is not warranted. Both bird collision with power lines and bird
collision with cooling towers are Category 1 issues.
- Because no threat to the stability of local wildlife populations or
vegetation communities is found for any cooling pond, the impacts are found to
be of small significance. Potential mitigation measures would include
excluding wildlife (e.g., birds) from contaminated ponds, converting to a dry
cooling system, or reducing plant output during fogging or icing conditions.
The impacts are found to be so minor that consideration of additional
mitigation measures is not warranted. These effects of cooling ponds are so
minor and so localized that cumulative impacts are not a concern. This is a
Category 1 issue.
- Maintaining power-line right-of-ways (ROWs) causes fluctuations in
wildlife populations, but the long-term effects are of small significance. The
staff found that bird collisions with transmission lines are of small
significance. Also, transmission line maintenance and repair would have
impacts of only small significance on floodplains and wetlands. In each case,
the staff found that potential mitigation measures beyond those implemented
during the current license term would be costly and provide little
environmental benefit, and thus are not warranted. These are Category 1
issues.
- Wildlife, livestock, and plants residing in power-line electromagnetic
fields (EMF) apparently grow, survive, and reproduce as well as expected in
the absence of EMF. The potential impact of EMF on terrestrial resources
during the license renewal term is considered to be of small significance for
all plants. Because the impact is of small significance and because mitigation
measures could create additional environmental impacts and would be costly, no
mitigation measures beyond those implemented during the current term license
would be warranted. This is a Category 1 issue.
- Land use restrictions are necessary within transmission-line ROWs. The
staff found these impacts to be of small significance at all sites. Mitigation
beyond that imposed when ROWs were established might include relocating the
transmission line. The staff concluded that such mitigation would not be
warranted because it would be very costly and provide little environmental
benefit. This is a Category 1 issue.
- During the license renewal term, the radiation dose commitment to the
total worker population is projected to increase less than 5 percent at
nuclear power plants under the typical scenario and less than 8 percent
at any plant under the conservative scenario. The present operating experience
results in about 30,000 person-rem/year for all licensed plants combined.
After the period of refurbishment, routine operating conditions are expected
to result in 32,000 person-rem/year for all plants combined. The risk
associated with occupational radiation exposures after license renewal is
expected to be of small significance at all plants. No mitigation measures
beyond those implemented during the current license term are warranted because
the existing ALARA process continues to be effective in reducing radiation
doses. This is a Category 1 issue.
- Among the 150 million people who live within 50 miles of a U.S. nuclear
power plant, about 30 million will die of spontaneous cancer unrelated to
radiation exposure from nuclear power plants. This number is compared with
approximately 5 calculated fatalities associated with potential
nuclear-power-plant-induced cancer. The estimated annual cancer risk to the
average individual is less than 1 x 10-6. Public
exposure to radiation during the license renewal term is of small significance
at all sites, and no mitigation measures beyond those implemented during the
current license term are warranted because current mitigation practices have
resulted in declining public radiation doses and are expected to continue to
do so. This is a Category 1 issue.
- The significance of potential for electrical shock from charges induced by
transmission lines that may occur during the license renewal term cannot be
evaluated generically because no National Electric Safety Code (NESC) review
was performed for some of the earlier licensed plants. For those that
underwent an NESC review, a change in the transmission line voltage may have
been made since issuance of the initial operating license, or changes in land
use since issuance of the original license could have occurred. This is a
Category 2 issue.
- There is no consensus among scientists on whether 60-Hz EMF have a
measurable human health impact. Because of inconclusive scientific evidence,
the chronic effects of EMF would be not be categorized as either a Category 1
or 2 issue. If NRC finds that a consensus has been reached that there are
adverse health effects, all license renewal applicants will have to address
EMF effects in the license renewal process.
- Occupational health questions related to thermophilic organisms like
Legionella are currently resolved using proven industrial hygiene
principles to minimize worker exposures to these organisms in mists of cooling
towers. Adverse occupational health effects associated with microorganisms are
expected to be of small significance at all sites. Aside from continued
application of accepted industrial hygiene procedures, no additional
mitigation measures beyond those implemented during the current license term
are warranted. This is a Category 1 issue.
- Thermophilic organisms may or may not be influenced by operation of
nuclear power plants. The issue is largely unstudied. However, NRC recognizes
a potential health problem stemming from heated effluents. Public health
questions require additional consideration for the 25 plants using cooling
ponds, lakes, canals, or small rivers because the operation of these plants
may significantly enhance the presence of thermophilic organisms. The data for
these sites are not now at hand, and it is impossible with current knowledge
to predict the level of thermophilic organism enhancement at any given site.
Thus, the impacts are not known and are site specific. Therefore, the
magnitude of the potential public health impacts associated with thermal
enhancement of N. fowleri cannot be determined generically. This is a
Category 2 issue.
- The principal noise sources at power plants (cooling towers and
transformers) do not change appreciably during the aging process. Because
noise impacts have been found to be small and generally not noticed by the
public, noise impacts are expected to be of small significance at all sites.
Because noise reduction methods would be costly, and given that there have
been few complaints, no additional mitigation measures are warranted for
license renewal. This is a Category 1 issue.
- The staff examined socioeconomic effects of nuclear power plant operations
during a license renewal period. Five of these would be of small significance
at all sites: education, public safety, social services, recreation and
tourism, and aesthetics. Because mitigation measures beyond those implemented
during the current license term are costly and would offer little benefit, no
additional mitigation measures are warranted. These are Category 1 issues.
Four of the socioeconomic effects were found to have moderate or large
significance at some sites: housing, transportation, public utilities
(especially water supply), and off-site land use. These are Category 2
issues. In addition, the statute (National Historic Preservation Act) requires
consultation; thus historic and archaeological resources are Category 2
issues.
Accidents
[ Prev
| Next
| Table
of Contents ]
- The environmental impacts of postulated accidents were evaluated for the
license renewal period in GEIS Chapter 5. All plants have had a previous
evaluation of the environmental impacts of design-basis accidents. In
addition, the licensee will be required to maintain acceptable design and
performance criteria throughout the renewal period. Therefore, the calculated
releases from design-basis accidents would not be expected to change. Since
the consequences of these events are evaluated for the hypothetical maximally
exposed individual at the time of licensing, changes in the plant environment
will not affect these evaluations. Therefore, the staff concludes that the
environmental impacts of design-basis accidents are of small significance for
all plants. Because the environmental impacts of design basis accidents are of
small significance and because additional measures to reduce such impacts
would be costly, the staff concludes that no mitigation measures beyond those
implemented during the current term license would be warranted. This is a
Category 1 issue.
- The staff concluded that the generic analysis of severe accidents applies
to all plants and that the probability-weighted consequences of atmospheric
releases, fallout onto open bodies of water, releases to groundwater, and
societal and economic impacts of severe accidents are of small significance
for all plants. However, not all plants have performed a site-specific
analysis of measures that could mitigate severe accidents. Consequently,
severe accidents are a Category 2 issue for plants that have not performed a
site-specific consideration of severe accident mitigation and submitted that
analysis for Commission review.
Uranium Fuel Cycle and Management of Waste
[ Prev
| Next
| Table
of Contents ]
- The radiological and nonradiological environmental impacts of the uranium
fuel cycle have been reviewed. The review included a discussion of the values
presented in Table
S-3, an assessment of the release and impact of 222Rn and of
99Tc, and a review of the regulatory standards and experience of
fuel cycle facilities. For the purpose of assessing the radiological impacts
of license renewal, the Commission uses the standard that the impacts are of
small significance if doses and releases do not exceed permissible levels in
the Commission's regulation. Given the available information regarding the
compliance of fuel-cycle facilities with applicable regulatory requirements,
the Commission has concluded the actual impacts of the fuel cycle are at or
below existing regulatory limits. Accordingly, the Commission concludes that
individual radiological impacts of the fuel cycle (other than the disposal of
spent fuel and high-level waste) are small. With respect to the
nonradiological impact of the uranium fuel cycle, data concerning land
requirements, water requirements, the use of fossil fuel, gaseous effluent,
liquid effluent, and tailings solutions and solids, all listed in Table
S-3, have been reviewed to determine the significance of the environmental
impacts of a power reactor operating an additional 20 years. The
nonradiological environmental impacts attributable to the relicensing of an
individual power reactor are found to be of small significance. The individual
radiological and the nonradiological effects of the uranium fuel cycle are
Category 1 issues.
The radiological impacts of the uranium fuel
cycle on human populations over time (collective effects) have been considered
within the framework of Table
S-3. The 100-year environmental dose commitment to the U.S. population
from the fuel cycle, high-level-waste and spent-fuel disposal excepted, is
calculated to be about 14,800 man-rem, or 12 cancer fatalities, for each
additional 20-year power-reactor operating term. Much of this, especially the
contribution of radon releases from mines and tailing piles, consists of tiny
doses summed over large populations. This same dose calculation can
theoretically be extended to include many tiny doses over additional thousands
of years as well as doses outside the United States. The result of such a
calculation would be thousands of cancer fatalities from the fuel cycle, but
this result assumes that even tiny doses have some statistical adverse health
effect that will not ever be mitigated (for example, no cancer cure in the
next thousand years) and that these dose projections over thousands of years
are meaningful. However, these assumptions are questionable. In particular,
science cannot rule out the possibility that there will be no cancer
fatalities from these tiny doses. For perspective, the doses are very small
fractions of regulatory limits and even smaller fractions of natural
background exposure to the same populations. No standards exist that can be
used to reach a conclusion as to the significance of the magnitude of the
collective radiological effects. Nevertheless, some judgment as to the
regulatory NEPA implication of this issue should be made, and it makes no
sense to repeat the same judgment in every case. The Commission concludes that
these impacts are acceptable in that these impacts would not be sufficiently
large to require the NEPA conclusion, for any plant, that the option of
extended operation under 10 CFR Part 54 should be eliminated.
Accordingly, while the Commission has not assigned a single level of
significance for the collective effects of the fuel cycle, this issue is
considered Category 1.
There are no current regulatory limits for
off-site releases of radionuclides from high-level-waste and spent-fuel
disposal at the current candidate repository site at Yucca Mountain. If we
assume that limits are developed along the lines of the 1995 National Academy
of Sciences report and that, in accordance with the Commission's Waste
Confidence Decision, a repository can and likely will be developed at some
site that will comply with such limits, peak doses to virtually all
individuals will be 100 mrem/year or less. However, while the Commission has
reasonable confidence that these assumptions will prove correct, there is
considerable uncertainty since the limits are yet to be developed, no
repository application has been completed or reviewed, and uncertainty is
inherent in the models used to evaluate possible pathways to the human
environment. The National Academy report indicates that 100 mrem/year should
be considered as a starting point for limits for individual doses but notes
that some measure of consensus exists among national and international bodies
that the limits should be a fraction of the 100 mrem/year. The lifetime
individual risk from 100-mrem/year dose limit is about 3 x
10-3. Doses to populations from disposal cannot now (or
possibly ever) be estimated without very great uncertainty. Estimating
cumulative doses to populations over thousands of years is more problematic.
The likelihood and consequences of events that could seriously compromise the
integrity of a deep geologic repository have been evaluated by the Department
of Energy (DOE) and the NRC, and other federal agencies have expended
considerable effort to develop models for the design and for the licensing of
a high-level-waste repository, especially for the candidate repository at
Yucca Mountain. More meaningful estimates of doses to population may be
possible in the future as more is understood about the performance of the
proposed Yucca Mountain repository. Such estimates would involve very great
uncertainty, especially with respect to cumulative population doses over
thousands of years. The standard proposed by the NAS is a limit on maximum
individual dose. The relationship of potential new regulatory requirements,
based on the NAS report, and cumulative population impacts has not been
determined, although the report articulates the view that protection of
individuals will adequately protect the population for a repository at Yucca
Mountain. However, EPA's generic repository standards in
40 CFR Part 191 generally provide an indication of the order of
magnitude of cumulative risk to population that could result from the
licensing of a Yucca Mountain repository, assuming the ultimate standards will
be within the range of standards now under consideration. The standards in
40 CFR Part 191 protect the population by imposing "containment
requirements" that limit the cumulative amount of radioactive material
released over 10,000 years. The cumulative release limits are based on EPA's
population impact goal of 1,000 premature cancer deaths worldwide for a
100,000-metric tonne (MTHM) repository.
Nevertheless, despite all the
uncertainty surrounding the effects of the disposal of spent fuel and
high-level waste, some judgment as to the regulatory NEPA implications of
these matters should be made, and it makes no sense to repeat the same
judgment in every case. Even taking the uncertainties into account, the
Commission concludes that these impacts are acceptable in that these impacts
would not be sufficiently large to require the NEPA conclusion, for any plant,
that the option of extended operation under 10 CFR Part 54
should be eliminated. Accordingly, while the Commission has not assigned a
single level of significance for the impacts of spent-fuel and
high-level-waste disposal, this issue is considered Category 1.
- The radiological and nonradiological environmental impacts from the
transportation of fuel and waste attributable to license renewal of a power
reactor have been reviewed. Environmental impact data for transportation are
provided in Table S-4.
The estimated radiological effects are within the Commission's regulatory
standards. Radiological impacts of transportation are therefore found to be of
small significance when they are within the range of impact parameters
identified in Table
S-4. The nonradiological impacts are those from periodic shipments of fuel
and waste by individual trucks or rail cars and thus would result in
infrequent and localized minor contributions to traffic density. These
nonradiological impacts are found to be small when they are within the range
of impact parameters identified in Table
S-4. Programs designed to reduce risk, which are already in place, provide
for adequate mitigation. Table
S-4 should continue to be the basis for case-by-case evaluations of
transportation impacts of spent fuel until such time as detailed analysis of
the environmental impacts of transportation to the Yucca Mountain repository
becomes available. Transportation of fuel and waste is a Category 2 issue.
- The radiological and nonradiological environmental impacts from the
storage and disposal of low-level radiological waste attributable to license
renewal of a power reactor have been reviewed. The comprehensive regulatory
controls that are in place and the low public doses being achieved at reactors
ensure that the radiological impacts to the environment will remain small
during the term of the renewed license. The maximum additional on-site land
that may be required for low-level waste storage during the term of a renewed
license and associated impacts will be small. Nonradiological environmental
impacts on air and water will be negligible. The radiological and
nonradiological environmental impacts of long-term disposal of low-level waste
from any individual plants at licensed sites are small. The need for the
consideration of mitigation alternatives within the context of renewal of a
power reactor license has been considered, and the Commission concludes that
its regulatory requirements already in place provide adequate mitigation
incentives for on-site storage of low-level waste and that, for off-site
disposal, mitigation would be a site-specific consideration in the licensing
of each facility. In addition, the Commission concludes that there is
reasonable assurance that sufficient low-level waste disposal capacity will be
made available when needed for facilities to be decommissioned consistent with
NRC decommissioning requirements. Low-level waste is a Category 1 issue.
- The radiological and nonradiological environmental impacts from the
storage and disposal of mixed waste attributable to license renewal of a power
reactor have been reviewed. The comprehensive regulatory controls and the
facilities and procedures that are in place ensure proper handling and
storage, as well as negligible doses and exposure to toxic materials for the
public and the environment at all plants. License renewal will not increase
the small, continuing risk to human health and the environment posed by mixed
waste at all plants. The radiological and nonradiological environmental
impacts of long-term disposal of mixed waste from any individual plant at
licensed sites are small. The maximum additional on-site land that may be
required for mixed waste is a small fraction of that needed for low-level
waste storage during the term of a renewed license, and associated impacts
will be small. Nonradiological environmental impacts on air and water will be
negligible. The radiological and nonradiological environmental impacts of
long-term disposal of mixed waste from any individual plants at licensed sites
are small. The need for the consideration of mitigation alternatives within
the context of renewal of a power reactor license has been considered, and the
Commission concludes that its regulatory requirements already in place provide
adequate mitigation incentives for on-site storage of mixed waste and that,
for off-site disposal, mitigation would be a site-specific consideration in
the licensing of each facility. In addition, the Commission concludes that
there is reasonable assurance that sufficient mixed waste disposal capacity
will be made available when needed for faculties to be decommissioned
consistent with NRC decommissioning requirements. Mixed waste is a Category 1
issue.
- The Commission's waste confidence finding at 10 CFR 51.23 leaves only the
on-site storage of spent fuel during the term of plant operation as a
high-level waste storage and disposal issue at the time of license renewal.
The Commission's regulatory requirements and the experience with on-site
storage of spent fuel in fuel pools and dry storage have been reviewed. Within
the context of a license renewal review and determination, the Commission
finds that there is ample basis to conclude that continued storage of existing
spent fuel and storage of spent fuel generated during the license renewal
period can be accomplished safely and without significant environmental
impacts. Radiological impacts will be well within regulatory limits; thus
radiological impacts of on-site storage meet the standard for a conclusion of
small impact. The nonradiological environmental impacts have been shown to be
not significant; thus they are classified as small. The overall conclusion for
on-site storage of spent fuel during the term of a renewed license is that the
environmental impacts will be small for each plant. The need for the
consideration of mitigation alternatives within the context of renewal of a
power reactor license has been considered, and the Commission concludes that
its regulatory requirements already in place provide adequate mitigation
incentives for on-site storage of spent fuel. On-site storage of spent fuel
during the term of a renewed operating license is a Category 1 issue.
- The environmental impacts from the storage and disposal of nonradiological
waste attributable to the license renewal of a power reactor have been
reviewed. Regulatory and operational trends suggest a gradual decrease in
quantities generated annually and the impacts during the terms of renewed
licenses. Facilities and procedures are in place to ensure continued proper
handling and disposal at all plants. Consequently, the generation and
management of solid nonradioactive waste during the term of a renewed license
is anticipated to result in only small impacts to the environment. Because the
facilities and procedures that are in place are expected to ensure continued
proper handling and disposal at each plant, additional mitigative measures are
not a consideration in the context of a license renewal review.
Nonradiological waste is a Category 1 issue.
Decommissioning
[ Prev
| Next
| Table
of Contents ]
- Decommissioning after a 20-year license renewal would increase the
occupational dose no more than 0.1 person-rem (compared with 7,000 to 14,000
person-rem for DECON decommissioning at 40 years) and the public dose by
a negligible amount. License renewal would not increase to any appreciable
extent the quantity or classification of LLW generated by decommissioning. Air
quality, water quality, and ecological impacts of decommissioning would not
change as a result of license renewal. There is considerable uncertainty about
the cost of decommissioning; however, while license renewal would not be
expected to change the ultimate cost of decommissioning, it would reduce the
present value of the cost. The socioeconomic effects of decommissioning will
depend on the magnitude of the decommissioning effort, the size of the
community, and the other economic activities at the time, but the impacts will
not be increased by decommissioning at the end of a 20-year license renewal
instead of at the end of 40 years of operation. Incremental radiation
doses, waste management, air quality, water quality, ecological, and
socioeconomic impacts of decommissioning due to operations during a 20-year
license renewal term would be of small significance. No mitigation
measures beyond those provided by ALARA are warranted within the context of
the license renewal process. The impacts of license renewal on radiation
doses, waste management, air quality, water quality, ecological resources, and
socioeconomics impacts from decommissioning are Category 1 issues.