July 2000
Key Facts
- All the used nuclear fuel from nuclear power plants is
in solid form. A typical nuclear power plant produces about
20 metric tons of used uranium fuel each year. All the used
fuel produced by the U.S. nuclear energy industry in 40
years of operation—some 40,000 metric tons—would, if stacked
end to end, cover an area the size of a football field to a
depth of about five yards.
- Used fuel is stored at nuclear power plant sites, either
in steel-lined, concrete pools filled with water or in dry
containers—aboveground steel or steel-reinforced concrete
containers with steel inner canisters. On-site storage is an
interim measure, however. Although the Nuclear Regulatory
Commission (NRC) determined that used fuel could be stored
at plant sites for 100 years without adverse health or
safety consequences, permanent disposal is necessary.
- The Nuclear Waste Policy Act of 1982 and its 1987
amendments require or authorize the Department of Energy
(DOE) to locate, build and operate a deep, mined geologic
repository for high-level waste and a facility for interim
storage of used fuel, as well as a transportation system
that safely links U.S. nuclear power plants, the interim
storage facility and the permanent repository.
- The act's 1987 amendments designated Yucca Mountain in
Nevada for study as a possible repository site, and DOE is
conducting a comprehensive scientific investigation of its
usefulness as a repository. The repository, which was to
have been completed by 1998, is at least 12 years behind
schedule, and no site has been selected for an interim
storage facility.
- On Jan. 31, 1998, the federal government defaulted on
its obligation—under the act and pursuant to contracts
between utilities and DOE—to begin moving used fuel from the
nation's nuclear power plants.
Solid Used Fuel: Small Volumes, Safely Stored
To generate electricity, nuclear power plants use uranium
oxide. This fuel—in the form of small ceramic pellets—is
placed inside metal fuel rods. These rods are grouped into
bundles called assemblies. Fission—the splitting of uranium
atoms in a chain reaction—produces a tremendous amount of heat
energy for the amount of material consumed. This energy is
used to boil water into steam, which drives a turbine
generator to produce electricity.
Every 18-24 months, the plant is shut down and the oldest
fuel assemblies-which have released their energy but have
become intensely radioactive as a result of fission-are
removed and replaced.
All of the country's nuclear power plants together produce
about 2,000 metric tons of used fuel annually. Today, this
used fuel is stored at the plant sites, either in used fuel
pools or dry storage.
The Nuclear Waste Policy Act of 1982 and 1987
The Nuclear Waste Policy Act of 1982 and its 1987
amendments require or authorize DOE to:
- locate, build and operate a deep, mined geologic
repository for high-level waste
- locate, build and operate a facility for interim storage
of used fuel
- develop a transportation system that safely links U.S.
nuclear power plants, the interim storage facility and the
permanent repository.
The act provided for the Environmental Protection Agency to
set radiation standards for the repository and for the Nuclear
Regulatory Commission to license all facilities and
transportation containers.
The act also created the Nuclear Waste Technical Review
Board, comprising 10 members appointed by the president from
nominations made by the National Academy of Sciences, to serve
as an independent source of expert advice on technical and
scientific aspects of DOE's waste program.
To pay for a permanent repository, an interim storage
facility and the transportation of used fuel, the Nuclear
Waste Policy Act established the Nuclear Waste Fund. Since
1982, electricity consumers have paid into the fund a fee of
one-tenth of a cent for every nuclear-generated kilowatt-hour
of electricity consumed. By the end of June 2000, these
customer commitments plus interest totaled more than $17
billion.
To comply with the requirement to locate and build a
high-level waste repository, DOE selected nine locations in
six states that met its criteria for consideration as
potential repository sites. Technical studies and
environmental assessments narrowed this field to five and then
three sites: Yucca Mountain, Nev., Deaf Smith County, Texas,
and Hanford, Wash.
In its 1987 amendments to the Nuclear Waste Policy Act,
Congress selected Yucca Mountain as the sole site to undergo
an extensive scientific study process called "site
characterization."
The start of site characterization was delayed for several
reasons, among them the refusal of Nevada to issue the
environmental permits needed for surface-disturbing work such
as maintaining roads, digging trenches and drilling boreholes.
In 1989, DOE announced that the opening date for a repository
would be delayed until 2010—12 years later than originally
promised.
Meanwhile, no site was selected for an interim storage
facility, and the federal government defaulted on a
longstanding obligation to begin moving used fuel from the
nation's nuclear plants by January 1998.
The Permanent Repository: Focus on Yucca
Mountain
Site characterization at Yucca Mountain has been one of the
most thorough and comprehensive scientific investigations ever
conducted, lasting two decades, costing $6.4 billion and
involving thousands of scientists, engineers and technicians.
Inside Yucca Mountain, DOE built an Exploratory Studies
Facility—a system of tunnels that allows scientists to conduct
seismological, geological and hydrological studies. The
five-mile tunnel was completed in 1997. Since then, scientists
have conducted numerous tests in the tunnel, examining the
rocks that make up the potential repository, studying the
movement of the small amount of water that flows through the
mountain and simulating the reaction of rock and water to the
heat released by used fuel. The data from these tests have
helped scientists design the repository and assess its
performance.
DOE is using the results from its scientific investigation
to evaluate Yucca Mountain's potential to perform as an
effective repository for used nuclear fuel and high-level
radioactive waste. The agency has released two reports that
present this information to decision makers and the public.
Yucca Mountain Viability Assessment. The
viability assessment—a roadmap of completed and planned
scientific and engineering work—was issued in December 1998.
It included a design for the repository and explained how it
will work, what it will take to license it and how much it
will cost. The assessment concluded that the remote desert
site was well suited for a geologic repository and that the
ongoing work—to reach a decision in 2001 on whether or not to
recommend the site—should proceed.
Draft Environmental Impact Statement. In
August 1999, DOE issued a draft environmental impact
statement-as required by the National Environmental Policy
Act. The statement found a repository's environmental impacts
to be so small as to have no adverse impact on public health
and safety. Following several months of public hearings around
the country, as well as comments from stakeholders, DOE began
work on the final environmental impact statement, which will
be issued—together with the agency's final site
recommendation—to the president in 2001.
The Site Approval Process. Under the Nuclear
Waste Policy Act, DOE is required to make a formal finding of
suitability for the Yucca Mountain site. The public will have
an opportunity to review the basis for that finding and
provide comments to DOE when the agency releases its draft
site recommendation consideration report in late 2000. If the
finding is favorable, the secretary of energy will recommend
to the president that the repository be built. That
recommendation is scheduled for July 2001. If the president
approves the recommendation, scheduled for January 2002, DOE
will apply in March 2002 to the Nuclear Regulatory Commission
for a license to build it. At this point, the state of Nevada
can submit a "notice of disapproval," which can be overruled
only by a majority vote in Congress.
NRC licensing review of DOE's application provides for the
participation of state and local governments, individuals and
interested organizations. NRC approval is required before DOE
can begin building the repository. In addition, the NRC must
approve repository operation and it also must approve final
repository closure (once all the waste is placed in the
repository).
Interim Storage: On Site
The lack of a repository
has placed nuclear power plants in the position of storing
more used fuel than expected for longer than originally
intended. The result is that many nuclear plants-which each
produce an average of about 20 metric tons of used fuel
annually-are running out of storage capacity. By the end of
2006, about 60 units will have no more storage space in their
used fuel pools, and by the end of 2010, 78 will have
exhausted their storage capacity.
When a plant's used fuel pool nears its designed capacity,
a utility has two options.
The Re-Racking Option.Typically, the first
choice is to re-rack the used fuel pool, moving the stored
assemblies closer together.
More than 130 re-rackings have been done at various nuclear
plant sites, but re-racking has its limitations. Strict
requirements exclude the possibility of unintended nuclear
chain reactions, prevent overheating of the pool, and ensure
that the pool's structural/earthquake resistance capability is
not exceeded. These requirements restrict the extent to which
the assemblies can be moved closer together, thus limiting the
additional space that can be gained.
Eventually, used fuel pools reach their capacity. Building
a new used fuel pool is not an option. It is too costly and
almost impossible to fit a new pool into the plant layout.
Although a few companies have shipped used fuel from one plant
to another with extra storage capacity, this option obviously
is not available to everyone. Most nuclear plants have used
the additional pool capacity gained by re-racking, and a
growing number have built or are building dry storage
facilities on site.
The Dry Storage Option. A number of nuclear
plants are storing used fuel in large, rugged containers made
of steel or steel-reinforced concrete, 18 or more inches
thick. The containers use materials like steel, concrete and
lead—instead of water—as a radiation shield. Depending on the
design, a dry container can hold from seven to 56 12-foot-long
fuel assemblies.
The NRC has approved several designs for use by utilities.
The containers have a 20-year license. After 20 years they
must be inspected, and with NRC approval the license could be
extended. Various dry storage technologies are being
successfully used by utilities today.
Loaded containers are filled with an inert gas, sealed and
stored either on reinforced concrete pads or inside
steel-reinforced concrete bunkers. The containers are designed
to withstand natural disasters such as tornadoes, hurricanes
and floods, and to prevent the release of radioactivity. The
designs require no mechanical devices for cooling and
ventilation.
Political Concerns. As nuclear plant
operating companies contemplate the use of dry storage, some
are finding political issues even more problematic than cost
issues. State and local officials are concerned that, unless
DOE fulfills its legal obligation to provide used fuel storage
and/or disposal, used fuel may have to remain in on-site dry
storage facilities beyond the envisioned 20-40 year period.
This would prevent some nuclear plant sites from being used
for other purposes after the plants are decommissioned. For
these reasons, some state governments have opposed the
licensing of additional dry storage, even though the
facilities are proven safe.
Cost Concerns. Designing, building and
licensing a dry storage facility at a plant site requires an
initial investment of $10-20 million. Once the facility is
operational, it will cost $5-7 million a year to add
containers as storage needs grow and to maintain the facility.
These costs are above and beyond the contributions that
electricity consumers already have made into the Nuclear Waste
Fund, established to pay for used fuel disposal. As a result
of DOE's default on its Jan. 31, 1998, obligation to begin
moving used fuel from nuclear power plants, utility customers
may have to pay an additional $5-7 billion for used fuel
management (assuming the repository is available beginning in
2010).
Interim Storage: Centralized off Site
Until a
repository is ready to accept used fuel from nuclear power
plants, the United States needs a centralized storage
facility. This facility would provide added safety and
security by using a single dedicated site, rather than leaving
used fuel at more than 70 locations across the country.
Private Interim Storage Facility.In the
absence of a federal centralized interim storage facility, a
group of utilities, led by Northern States Power Co., signed
an agreement in late 1996 with the Skull Valley Band of
Goshutes for a possible privately financed used fuel storage
facility on the tribe's land in Utah. The group applied for a
20-year operating license with the NRC in 1997. If approved, a
storage facility could begin operating by mid-2002.
Transportation of Used Nuclear Fuel
Used nuclear
fuel will be transported from nuclear power plants to storage
and disposal facilities either by rail, by truck or, part of
the way, by barge.
The transportation containers used to ship used fuel
typically have walls one-foot thick with shielding materials
sandwiched between outer and inner metal shells. Those
designed for truck transportation weigh between 25 and 40
tons, and carry one to seven used fuel assemblies. Railroad
containers weigh up to 125 tons and carry more than 25
assemblies.
To ensure that the transportation containers retain their
integrity in the event of an accident, they are designed to
withstand a consecutive series of highly destructive tests: a
30-foot fall onto a flat, unyielding surface; a 40-inch drop
onto a vertical steel rod; exposure to a 1,475° F fire for 30
minutes; and submersion under three feet of water for eight
hours. NRC studies showed that the engineering requirements
create forces more destructive than would occur in actual
accidents. Actual tests-conducted to examine the accuracy of
computer models and scale-model tests to analyze the ability
of containers to withstand the most severe accidents-drove
containers into unyielding concrete walls at more than 65
miles per hour, simulated 80-mph train crashes and exposed
containers to fully engulfing fires. The containers used in
these brutal tests survived intact, and the computer codes and
scale models were verified.
During the past 30 years, more than 3,000 shipments of used
fuel have been safely completed in the United States, and 10
times that number in other countries. While vehicle accidents
have occurred, there has not been a release of radioactive
materials or a single injury attributed to the radioactive
nature of the cargo. When the federal government finally opens
an interim storage facility or a permanent repository, the
number of used fuel shipments is expected to range from 300 to
500 per year.
Consensus on Safety of Long-Term Disposal
Since the 1950s, scientific organizations around the world
have examined the issue of radioactive waste management. Most
organizations-from the National Academy of Sciences and the
Office of Technology Assessment in the United States to the
International Atomic Energy Agency (IAEA) and the Organization
for Economic Cooperation and Development's Nuclear Energy
Agency (OECD/NEA)-have reached the same conclusion. They
believe that the best and safest long-term option for dealing
with high-level radioactive waste is deep geologic disposal.
Here is a sampling of the studies on geologic disposal:
1957: "We stress that the necessary geologic
investigation of any proposed site must be completed and the
decision as to a safe disposal means established before
authorization for construction is given."
- National Academy of Sciences-National Research
Council, Committee on Waste Disposal, Report on Disposal of
Radioactive Waste on Land
1978: "Effective long-term isolation for used fuel,
high-level or transuranic waste can be achieved by geologic
emplacement. We recommend emplacement of high-level and
transuranic wastes in a geologic repository."
- American Physical Society’s Study Group on Nuclear
Fuel Cycles and Waste Management
1981: "While various concepts have been proposed and
studied, it is generally agreed that underground disposal,
with the wastes appropriately immobilized, should provide the
necessary protection for man and the environment from the
potential hazard they pose."
- International Atomic Energy Agency "Underground
Disposal of Radioactive Wastes. Basic Guidance"
1985: "The disposal of radioactive waste in mined
geologic repositories at depths from 1,000 to several thousand
feet below the Earth’s surface is the final isolation
technology most widely studied and favored by the worldwide
scientific community. Three decades of study have revealed no
insurmountable technical obstacles to the development of mined
geologic repositories, provided suitable sites are found."
- Office of Technology Assessment, Managing the
Nation’s Commercial High-Level Radioactive Waste
1985: "There is a high degree of confidence in the
ability to design and operate disposal systems in deep
geological structures which will assure long-term isolation
for high-level waste or spent fuel and meet the relevant
long-term safety objectives."
- Radioactive Waste Management Committee of OECD/NEA,
Technical Appraisal of the Current Situation in the Field of
Radioactive Waste Management
1986: "There is consensus in the community that
isolation of wastes will be ensured by way of a multibarrier
disposal system. And there is broad agreement that disposal in
underground repositories is the preferred approach."
- IAEA Symposium on Siting, Design and Construction of
Underground Repositories for Radioactive Wastes, concluding
overview statement
1988: "The committee reaffirms its confidence in
geological disposal for long-lived and high-level radioactive
waste. Geological disposal is considered to be both feasible
and safe in the short and long term."
- Radioactive Waste Management Committee of OECD/NEA,
Geological Disposal of Radioactive Waste: In situ Research
and Investigations in OECD Countries
1990: "There is no scientific or technical reason to
think that a satisfactory geological repository cannot be
built."
- National Research Council’s Board on Radioactive
Waste Management, Rethinking High-Level Radioactive Waste
Disposal
1999: "Substantial scientific and technical progress
towards implementation of geologic disposal has been made in
the last 10 years, thanks to the extensive work carried out in
national programmes. … Opinions expressed by a wide
cross-section of waste management experts thus confirm the
consensus view that, at present and for the foreseeable
future, geologic disposal represents the only truly available
option for assuring safety and security over several tens of
thousands of years and more."
- Radioactive Waste Management Committee of OECD/NEA,
Progress Towards Geologic Disposal of Radioactive Waste:
Where Do We Stand?
The Archaeological Record
Nature also provides compelling evidence that high-level
waste can be contained geologically for hundreds of thousands,
even millions, of years. One of the best examples of nature's
ability to safely isolate radioactive elements over millions
of years is provided by the natural nuclear reactors
discovered in 1972 at the Oklo uranium mine in the West
African republic of Gabon.
This deposit of ore, which contained from 10 percent to 60
percent uranium, constituted a natural nuclear reactor.
Millions of years ago, it began a self-sustaining chain
reaction. Like all reactors, this one created its own
high-level waste—12,000 pounds of used fuel.
The Oklo chain reaction occurred intermittently for more
than 500,000 years. Despite its location in a wet, tropical
climate, Oklo's uranium deposit and high-level waste have
remained securely locked in this natural repository for the
past 200 million years. Many of the waste products stayed
where they were created or moved only a few inches before
decaying into harmless products.