|
Our National Forests Roadless Area
Policy
TWS Overview of USFS Roadless Area Protection Policy Final
Environmental Impact Statement
(FEIS)
|
Acreage
The total amount of inventoried
roadless land receiving immediate protection under the roadless
policy has grown from 42.2 million acres to 49.2 million acres (not
including the 9.3 million acres in the Tongass National Forest, see
below). The increased acreage is largely due to the inclusion of two
categories of land that were excluded from the draft policy: (1)
roadless areas within "specially designated areas," such as National
Recreation Areas, and (2) "roaded portions of inventoried roadless
areas," totaling approximately 2.8 million acres (p. 2-23). These
latter two changes are important because road building is allowed in
some specially designated areas (such as the Hells Canyon NRA), and
because there will no longer be a question about whether additional
road building would be allowed in and around roaded portions of
roadless areas. Once the policy goes into effect for the Tongass in
April 2004, a total of 58.5 million acres of inventoried roadless
land will be protected.
Logging
The preferred
alternative prohibits logging except for "stewardship" purposes.
According to the final EIS, the ban on commodity-purpose logging
would immediately reduce the amount of timber offered for sale in
roadless areas from 220 million board feet (mmbf) per year to 140
mmbf (a 36% reduction), of which 108 mmbf would come from the
Tongass National Forest (p. S-31, S-39). After April 2004, when the
prohibitions would take effect on the Tongass, the annual timber
sale volume in roadless areas would drop to 32 mmbf (S-31), which is
85% less than the 220 mmbf national total.
The allowance for
stewardship logging could be a significant loophole for
environmentally destructive logging. For example, salvage logging is
commonly classified as stewardship, even though Forest Service
scientists acknowledge it is often detrimental to forest and stream
ecosystems. Indeed, the Forest Service considers most of its current
timber sales to be primarily for stewardship purposes (p. 3-199).
The final EIS states that stewardship logging must "maintain or
improve roadless characteristics" and also satisfy at least one of
three conditions: (1) improve endangered or sensitive species
habitat, (2) reduce the risk of uncharacteristically intense fire,
or (3) restore ecological structure, function, processes, or
composition (p. 2-7). Road construction would not be permitted in
conjunction with stewardship sales, unless it was needed to protect
public health and safety.
Tongass National Forest
Although the preferred alternative claims that "the Tongass
National Forest would be treated the same as all other forests in
the National Forest System" (p. 2-14), the ban on roadbuilding and
logging would not take effect on the Tongass until April 2004. Until
then, the Forest Service would continue to build 61 miles of new
roads and offer 108 mmbf of timber sales on 2,800 acres in roadless
areas each year (p. S-38, S-39). After April 2004, the overall
timber sale program on the Tongass would drop 61% - from 176 mmbf to
68 mmbf (p. S-39). The Forest Service would implement an economic
transition program for communities in southeast Alaska and elsewhere
that are affected by the roadless policy.
Unroaded Areas
and Additional Protection
The final EIS eliminates all
of the "procedural" alternatives in the draft EIS, which would have
required the Forest Service to evaluate and consider protecting
"unroaded" areas and to consider additional protection for
inventoried roadless areas. Instead, the Forest Service has decided
to incorporate those requirements into the regular forest planning
process through final regulations that were promulgated on November
9 (65 Fed. Reg. 67513, 36 C.F.R. 219.9(b)(8)). The planning
regulations direct agency officials to identify, evaluate, and
consider protecting roadless and unroaded areas while revising
forest plans (p. 1-20). In addition, the final EIS indicates that
the impending final roads policy will limit road construction in
unroaded areas adjacent to inventoried roadless areas by requiring
agency officials to demonstrate a "compelling need" for the road.
Exceptions
The final EIS adds two more
exceptions to the general prohibition on road construction and
reconstruction. First, reconstruction is allowed if "needed to
implement road safety projects on roads determined to be hazardous
on the basis of accident experience or accident potential." For
example, a road could be realigned to eliminate a dangerous hairpin
turn on a road connecting two communities (p. 2-9). Second, State
highway projects crossing national forest lands and approved by the
Secretary of Agriculture would be exempt. Presently, there is only
one such highway project planned in the next five years - a 5.5-mile
highway relocation in Alaska's Chugach National Forest (p. 3-33).
The final EIS ominously mentions a much broader exception
for development of "leasable" minerals (e.g., oil, gas, coal, and
phosphate), but it is not included in the preferred alternative. The
potential exception would apply where "a road is needed for
prospective mineral leasing activities in inventoried roadless
areas" (p. 2-9). While omitted from the preferred alternative, the
final EIS states that the final rule "may or may not include" the
leasable minerals exception (p. 2-8). Areas where leasable mineral
activities are an issue include the Caribou National Forest in Idaho
(phosphate), Manti-LaSal National Forest in Utah (coal), and Little
Missouri National Grasslands in North Dakota (oil and gas) (p. 3-314
to 3-316).
Despite efforts by the downhill skiing industry
to obtain an exception for ski area developments, the final EIS
continues to apply the prohibition on road building to roadless land
located outside existing ski area permit areas.
| |