Copyright 2001 eMediaMillWorks, Inc.
(f/k/a Federal
Document Clearing House, Inc.)
Federal Document Clearing House
Congressional Testimony
March 28, 2001, Wednesday
SECTION: CAPITOL HILL HEARING TESTIMONY
LENGTH: 4747 words
COMMITTEE:
HOUSE ENERGY AND COMMERCE
HEADLINE:
TESTIMONY SAFE DRINKING WATER
TESTIMONY-BY: PERRY
BEIDER , PRINCIPAL ANALYST
AFFILIATION: CONGRESSIONAL
BUDGET OFFICE
BODY: March 28, 2001 The House
Committee On Energy and Commerce W.J. Billy Tauzin, Chairman Subcommittee on
Environment and Hazardous Materials Hearing Drinking Water Needs and
Infrastructure Mr. Perry Beider Principal Analyst Congressional Budget Office
SUMMARY The existing estimates of how much investment in drinking
water
infrastructure will be needed over the next 20 years are very uncertain
and may be too large. The lion s share of the investment will be used to
rehabilitate or replace water pipes, but there is no national inventory of pipes
ages and conditions on which to base estimates of investment needs. In the
absence of such an inventory, analysts have to rely on rough national
assumptions, which add significantly to the uncertainty inherent in any 20-year
projection. Moreover, notwithstanding claims that the existing estimates are, if
anything, likely to underestimate the needs, CBO has identified some factors
suggesting that those estimates may be too large. Thus, policymakers should not
give undue credence to the estimates of future needs or the associated funding
gaps. Moreover, the very concept of an investment need is a fuzzy one. The
amount of money that water systems must spend in order to provide the necessary
services can vary dramatically depending on how efficiently the systems operate
and invest. Therefore, from the standpoint of economic efficiency, it is
important that any federal support for
water infrastructure be
provided in a way that gives system operators and water users the appropriate
incentives to keep costs and usage down. Mr. Chairman and Members of the
Subcommittee, thank you for inviting me to testify. The Congressional Budget
Office (CBO) appreciates this opportunity to contribute to your review of the
needs for investment in drinking
water infrastructure. My
testimony today reflects some initial findings from an ongoing CBO study
requested by this Subcommittee and your colleagues on the Transportation and
Infrastructure Committee. Safe drinking water is essential to the economy and to
human health. But how much and how to invest in order to maintain an adequate
drinking
water infrastructure are difficult issues. I hope to
shed some light on those issues today. In particular, I want to impart two main
points: First, the existing estimates of how much investment will be needed over
the next 20 years are very uncertain and may be too large. The lion s share of
the investment will be used to rehabilitate or replace water pipes, but there is
no national inventory of pipes ages and conditions on which to base estimates of
investment needs. In the absence of such an inventory, analysts have to rely on
rough national assumptions, which add significantly to the uncertainty inherent
in any 20- year projection. Moreover, notwithstanding claims that the existing
estimates are, if anything, likely to underestimate the needs, CBO has
identified some factors suggesting that those estimates may be too large. Thus,
policymakers should not give undue credence to the estimates of future needs or
the associated funding gaps. Second, the very concept of an investment need is a
fuzzy one. The amount of money that water systems must spend in order to provide
the necessary services can vary dramatically depending on how efficiently the
systems operate and invest. Therefore, from the standpoint of economic
efficiency, it is important that any federal support for
water
infrastructure be provided in a way that gives system operators and
water users the appropriate incentives to keep costs and usage down. THE
EXISTING ESTIMATES OF DRINKING WATER NEEDS Projecting 20 years into the future
is always difficult. Even the best 20-year estimate is only an extrapolation of
what would happen under current and currently anticipated trends. In the case of
projecting the needs for investment in
water infrastructure,
the difficulty is compounded by a shortage of data. The Environmental Protection
Agency s (EPA s) quadrennial Drinking
Water Infrastructure
Needs Survey provides relevant data collected from systems around the country.
However, EPA s reports based on the survey note that it underestimates
infrastructure needs over its 20-year horizon because many systems are not able
to identify and document all of their needs for the full period. 1 According to
EPA staff, follow-up visits to some systems after the first drinking water
survey yielded revised estimates that averaged 55 percent above those initially
reported. Prompted in part by the incompleteness of EPA s survey, a consortium
called the
Water Infrastructure Network (WIN) has developed
more comprehensive estimates of 20-year infrastructure needs, supplementing the
data from the survey with assumptions based on professional judgments. According
to WIN s estimates, shown in Table 1, investment needs for drinking water will
average about $24 billion per year through 2019 (expressed in 1997 dollars and
including financing costs). WIN estimates that capital spending in 1996 from all
sources-primarily local funds from ratepayers but also federal and state aid-was
roughly half of the estimated future needs; thus, relative to the 1996
investment level, future needs for drinking
water
infrastructure represent an average annual funding gap of $11 billion.
2 (The table also shows WIN s estimates of average annual spending for operation
and maintenance O&M . Because little outside funding is available for
O&M, ratepayers cover almost all of those costs as well as a portion of
capital costs; thus, the O&M estimates bear on the question of total costs
facing future ratepayers.) EPA is also conducting a similar gap analysis but has
not yet published its results. Uncertainty of the Estimates The assumptions and
judgments required in the absence of detailed data increase the uncertainty
surrounding the estimates. The analysis underlying WIN s estimate illustrates
that uncertainty. Part of that analysis comes from a 1998 report done for the
American Water Works Association (AWWA), which focused only on investments in
transmission and distribution systems and only on capital costs, not financing
or O&M. 3 The 1998 report estimated needs of $325.1 billion over 20 years
(an average of $16.3 billion per year), including $101.4 billion for large
systems, $198.0 billion for medium-sized systems, and $25.7 billion for small
systems. 4 The analysis took the figure for small systems directly from EPA s
1995 needs survey and estimated the other figures using probability
distributions to reflect uncertainty in four factors: the annual rate of pipes
replacement, the miles of pipe per water system, the distribution of pipes by
size, and the cost per foot of replacing pipes of each size. To reflect the
uncertainty about systems replacement of pipes, for example, the analysis
randomly selected replacement rates between 0.5 percent and 1.5 percent per
year. The resulting distributions of estimated needs were wide (see Table 2).
For medium-sized systems, the analysis found that the 80 percent confidence
interval around the mean estimate of $198 billion spanned $116 billion to $272
billion-leaving a 10 percent chance that the need was less than $116 billion and
another 10 percent chance that it exceeded $272 billion. For large systems, the
80 percent confidence interval spanned $19 billion to $193 billion-or from 82
percent below the mean to 91 percent above it. Notwithstanding those results,
CBO does not believe that the existing estimates of total needs for drinking
water investment are likely to be off by as much as 80 percent or 90 percent. 5
However, the results do illustrate the point that the use of assumptions in the
absence of hard data inevitably increases the imprecision of a future
projection. CBO further notes that the range of uncertainty around the needs
does not have to be plus or minus 80 percent to have a dramatic impact on the
potential scope of the policy problem that the needs represent. Because the
estimated funding gap for capital investment-that is, the amount above recent
funding levels-is roughly half of the total projected investment needs
(according to WIN s numbers), an error of, for example, 30 percent or 40 percent
in the projected needs translates to an error of 60 percent or 80 percent in the
funding gap. According to rough calculations by CBO, an error of 30 percent or
40 percent just in the assumptions about the necessary rate of replacing pipes,
which CBO believes is quite possible, could imply an error of 20 percent or 30
percent in the funding gap. 6 Similar estimates derived independently can raise
one s confidence in those estimates. Contrary to the common perception, however,
the current, preliminary version of EPA s gap analysis does not reach the same
conclusion as the WIN report. Although both analyses present estimated gaps of
$23 billion per year for drinking water and wastewater combined, that figure
means different things in the two cases: in the WIN analysis, it is the 20-year
average of a gap that grows year by year, whereas in EPA s preliminary analysis,
it is the gap at the end of the 20- year period. 7 The differences are
concentrated on the drinking water needs; for wastewater, the two estimates of
needs are indeed very similar, if not identical-but that is because they were
derived using the same methodology from the same consultants. In short, the two
drinking water estimates are independent but not similar, and the two wastewater
estimates are similar but not independent. Possible Biases in the Estimates
Given that the estimates of needs are surrounded by significant uncertainty, the
question arises as to whether that uncertainty is roughly balanced-that is,
whether the estimates are about equally likely to prove too low as too high, or
to lie primarily on one side or the other. WIN and EPA analysts argue that they
have deliberately erred on the low side in their assumptions on capital and
O&M spending and, therefore, that their estimates probably understate future
needs. In particular, they point to their assumptions that 25 percent of the
investment is financed without borrowing, that the rest is financed at a real
interest rate of 3 percent, and that increased efficiency reduces O&M costs
by 20 percent to 25 percent. Those assumptions are reasonably conservative. But
CBO has identified other factors that could tend to overstate the estimated
costs for capital investment, financing, and O&M: First, in estimating
needed capital investment, the existing analyses do not assume any savings from
improved efficiency. Although the data to support such savings are sparser than
they are for O&M, evidence from a growing number of case studies suggests
savings from methods such as design/build contracting, preventive maintenance,
and demand management (discussed below). Incorporating efficiencies in capital
investment would also reduce the estimates for financing and O&M costs,
because each dollar not invested cuts 75 cents from the debt to be financed and
reduces the capital stock to be operated and maintained. 8 Second, the financing
costs in the WIN report may be overstated. They appear to be the lifetime
debt-service payments associated with the average annual capital investment over
the period of 2000 to 2019. However, debt payments on investments made late in
the period will primarily occur after 2019 and therefore have little influence
on the average payment for debt service within the period. Conversely, the
amount of debt paid in much of the first decade will primarily reflect the level
of investment made before 2000, which is significantly lower than the level the
report recommends from 2000 on. According to CBO s rough calculations, under WIN
s assumptions the average annual debt service paid within the period would be
roughly 25 percent below the reported $5 billion. Third, the assumed reductions
in O&M costs resulting from increased efficiency are relative to a baseline
that may be too high for wastewater and perhaps for drinking water as well. CBO
does not have specific information on the methods used to calculate O&M
costs for drinking water systems, but the wastewater analysis used in both the
WIN report and EPA s preliminary study assumes that the baseline ratio of
O&M to capital stock rises steadily throughout the 20-year period,
extrapolating from a general trend in data from 1972 to 1996. Although
additional capital stock is typically associated with additional costs for
O&M, it is not obvious that the ratio of O&M to capital would continue
rising indefinitely in the absence of efficiency gains. Increases in that ratio
during the 1970s and 1980s may reflect unique causes, such as the initial
introduction of many secondary treatment facilities and biosolids disposal
programs. Going forward, some investments, such as those to replace deteriorated
pipes or install automated sensing and measurement equipment, could reduce the
O&M required per unit of capital stock. In short, there is much about future
investment needs in drinking
water infrastructure that is
unknown, and assumptions based on even the best professional judgments can be
significant sources of error. EFFICIENCY, EQUITY, AND THE DEFINITION OF NEED
Although considerable uncertainty surrounds the available estimates, CBO accepts
the judgment of industry professionals that drinking water systems will require
large investments over the next few decades. But future needs are not a
predetermined reality; they are partly the result of many federal, state, local,
and private choices yet to be made. The amount of investment needed to maintain
services and meet water quality requirements under current industry practices
and current government policy is likely to differ from the amount needed under
evolving industry practices, under alternative government policies, or under a
least-cost approach. In particular, a broad increase in federal funding intended
to help keep water rates affordable could reduce the pressure on systems to
operate more efficiently and on customers to economize on their use of water
services and thereby keep total investment needs higher than they would be
otherwise. That is another example of the familiar trade-off between equity and
efficiency. In recent years, both drinking water and wastewater systems around
the country have taken steps to become more efficient. The results are
illustrated by data from a survey conducted periodically by the Association of
Metropolitan Sewerage Agencies. For example, the average sum of O&M costs
and administrative costs per million gallons declined from $1,108 in the 1996
survey to $987 in the 1999 survey. 9 One method used to reduce costs has been
more efficient use of employees: among 45 municipal wastewater agencies that
responded in both 1996 and 1999, full-time-equivalent staffing per 10,000 people
in the served area declined from 5.0 to 4.7. 10 Experts in the water industry
see room for further cost savings, not only in operational costs but also in
capital costs. Promising methods include the following: ! Consolidation of
systems to achieve economies of scale. Reportedly, 50 percent of small drinking
water systems lie within a standard metropolitan statistical area. ! Asset
management, which involves analyzing local data on assets age, performance, and
condition in order to identify a maintenance and replacement strategy that
minimizes long-run costs. ! Demand management, including the use of pricing
strategies to reduce peak use. 11 ! Innovative contracting for new construction,
such as the use of contracts covering both design and construction, or even
design, construction, and operation. 12 But those potential future savings could
go unrealized if federal policy inadvertently undermines the forces pushing for
efficiency. The savings observed to date have occurred primarily because of
pressures from two sources. One source has been competition from private firms
seeking contracts to operate municipal systems. The actual or potential threat
of such competition has led to significant increases in efficiency in systems
that remain publicly operated as well as in those contracted out to private
operators. The second source of pressure has been resistance from customers and
oversight bodies to large rate increases. That pressure too has led system
operators to reexamine their management practices and find many ways to reduce
costs without sacrificing quality of service. Whether federal aid would
undermine or reverse the progress in water systems efficiency would depend on
how much aid the government provided and in what form. Clearly, if the federal
government issued blank checks for infrastructure, local systems would lose any
incentive to keep capital costs down. But the issue is also relevant in less
extreme cases: a 1985 CBO analysis found that high federal cost shares in the
original construction
grant program for wastewater treatment
raised capital costs by more than 30 percent. 13 Unfortunately, CBO cannot
describe the precise relationship between federal support and total nationwide
costs. But if it is not clear how much is too much federal aid from the
standpoint of efficiency, it is also not clear how little is too little for
equity purposes-that is, to address the affordability and fairness issues. A
large, broad program would probably benefit not only the neediest water users
but also well- off users, with little additional gain in equity. CBO is
analyzing the affordability issues associated with
water
infrastructure needs and expects to provide additional information on
them in a report to be issued later this year. In summary, CBO s analysis of the
existing estimates of investment needs for drinking
water
infrastructure leads the agency to conclude that those estimates are
accompanied by significant uncertainty and may be too high. Moreover, how big
the needs turn out to be will be influenced by who pays to meet them; in
particular, proposals intended to address the equity problem of keeping rates
affordable may adversely affect efficiency by raising total national costs.
LOAD-DATE: March 30, 2001, Friday