Copyright 2002 eMediaMillWorks, Inc.
(f/k/a Federal
Document Clearing House, Inc.)
Federal Document Clearing House
Congressional Testimony
May 1, 2002 Wednesday
SECTION: CAPITOL HILL HEARING TESTIMONY
LENGTH: 3171 words
COMMITTEE:
HOUSE TRANSPORTATION AND INFRASTRUCTURE
SUBCOMMITTEE: HIGHWAYS AND TRANSIT
HEADLINE: HIGHWAYS AND TRANSIT
TESTIMONY-BY: TOM STEPHENS, P.E., DIRECTOR
AFFILIATION: NEVADA DOT
BODY:
Testimony on "Major Project Management: Solutions for Major Success"
Presented by Nevada DOT Director Tom Stephens, P.E. on behalf of the
American Association of State Highway &
Transportation
Officials
for the United States House of Representatives Committee on
House
Transportation and Infrastructure Subcommittee on
Highways and Transit
on May 1, 2002
Mr. Chairman and Members of
the Committee, my name is Tom Stephens. For the past seven years I have been the
Director of the Nevada Department of
Transportation, and I am
here today to testify on behalf of the American Association of State Highway and
Transportation Officials (AASHTO) on project oversight issues.
I also serve as the President of the 18-state Western Association of State
Highway and
Transportation Officials (WASHTO). Additionally, I
chair the AASHTO Task Force on Project Oversight.
I want to thank you,
and this Committee, for your leadership in scheduling this hearing on a subject
that is of great importance to the States-- and I know of significance to the
Committee and the American public. The manner in which we assure adequate
project oversight is one that is of critical importance to the proper
functioning of the Federal-aid Highway Program. As a State DOT Director, I
believe that I can offer benefit of the experience I have gained in
administering projects. Let me begin by giving you some background on my state,
Nevada. We are by far the nation's fastest-growing state, having grown from less
than half a million people in 1970 to two million in 2000. Nearly all of this
growth has been in the urban areas, and we have successfully completed many
highway projects to meet the
transportation demands. The public
bus systems in the two urban areas have been greatly expanded, and a monorail
system is now under construction in Las Vegas. Clark County, where Las Vegas is
located, has a land area larger than New Jersey. Clark County grew by 85 percent
in the last decade. The
transportation challenges are
tremendous.
I am pleased to report that even with this dramatic growth
in design and construction activity in our state, we have been able to maintain
an excellent record on cost-control and project oversight. Still, we would like
to do better. Recently we audited Nevada's highway construction projects
completed in the last four years, and found that our change orders averaged 9
percent over the low-bid amount. We in Nevada have identified 10 areas where we
feel improvements could be made to reduce change orders. I include these areas
to give you some insight into the normal project level issues with some examples
of solutions which could benefit all projects, including the so called
"MEGAPROJECTS" which have been the subject of so much review in the past several
years.
The Nevada list is as follows:
1. Project Tracking needs
to be improved so we know what the level of change orders are at any given time
and can flag projects for special attention during construction.
2.
Design expertise has been lost in recent years, because of retirements and
inadequate salary levels (for example, 77 of our 111 roadway-design positions
turned over in 2000). The Nevada Legislature approved a 19 percent pay increase
for our engineers effective July 1, 2001.
3. Design manuals, checklists
and training need to be improved, especially in view of the inexperience of the
workforce, both in- house and with new consultant personnel.
4.
Construction inspection expertise has also dropped in recent years, and more
oversight of new resident engineers is needed. A new section is being
established in our Construction Division Headquarters to provide increased
review.
5. Geotechnical considerations have caused unanticipated costs,
and specifications have been changed to shift more of the risk to the
contractor.
6. Unbalanced bidding by contractors has taken advantage of
the "unit bid" nature of highway projects. (i.e. highway projects paid for based
on the contractor's unit-price bid on each item of work for actual quantities of
material provided, such as tons of asphalt, cubic yards of concrete, pounds of
steel etc.) Actual quantities often vary from plan quantities, and a contractor
may adjust his unit prices accordingly to take advantage of quantity overruns or
under-runs. In Nevada we have set up a procedure to review all projects for
unbalancing and have rejected bids for this reason. This procedure has recently
withstood court challenges.
7. Increasingly complex systems such as
traffic-control centers, high-tech traffic signals, and other intelligent
transportation system have been a special challenge and require
special attention.
8. Environmentally sensitive difficult locations,
such as the Lake Tahoe Basin, always seem to have higher costs and require
special attention during design as well as higher contingencies built into the
cost estimates.
9. Right-of-Way issues, especially utility relocations,
have caused significant delays during construction of new capacity projects.
Better surveying and advance utility relocation are essential.
Let me
now turn to the subject of this hearing-major project management from a national
prospective, which I will refer to as project oversight. AASHTO's Task Force on
Project Oversight was established to analyze issues in project oversight.
Working thorough AASHTO's many committees; we share good practices among the
states, develop guidance documents for the states, and formulate recommendations
that can be offered as part of AASHTO's
reauthorization
proposals. Those
reauthorization proposals will be considered
at AASHTO's Annual Meeting in October, and we will develop our recommendations
prior to that time.
History of Project Oversight: There has been a
continuing need for project oversight since the inception of the Interstate
System in 1956. The major issue that arose in that early period was fraud in the
highway program. The Federal government responded by creating the Special House
Subcommittee on the Federal-aid Highway Program (the Blatnick Committee), and
provided the resources necessary to assure that fraud cases were addressed.
AASHTO was a full partner in that effort, and AASHTO members worked to develop
new tools and oversight procedures to assure that all elements of project
oversight were addressed.
Specifically, AASHTO worked closely with the
Federal Highway Administration to develop software known as the Bid Analysis and
Management System (BAMS) which is part of a suite of project- management
software products that AASHTO has developed for the states to assist in overall
project management. This software can help state DOTs spot patterns in bidding
that may point to fraudulent activity.
AASHTO has been a key sponsor
with the U.S. Department of
Transportation of the biannual
National Fraud Conference, attended by representatives from virtually every
state. This conference brings together national leaders in this area, as well as
showcasing best practices from states on addressing fraud issues.
AASHTO
has long supported assuring that there is adequate inspection of projects under
construction, and has worked to assure that proper tools are available to
examine project cost changes resulting from changed conditions. AASHTO has also
disseminated information on best practices in project management, and continues
to work with its members to share that information.
The Congress has
focused on the projects that cost more than $
1 billion, and now
requires the development and approval of finance plans for those projects prior
to the approval of funding. AASHTO is working to provide technical assistance on
developing such plans, and will work with the State DOTs to assist in the
development.
However, the issues that gave rise to concerns for the cost
control on Megaprojects require more than finance plans. They require careful
oversight by qualified personnel at the Federal and state level. They also
require full disclosure of cost and scheduling information by contractors. We
have learned a great deal from recent experience, and we intend to incorporate
appropriate recommendations in our task force report.
Let me be more
specific. We need to assure that we create an environment which makes oversight
of Megaprojects a priority. That is, one that assures that we carefully consider
the appropriate process for oversight of this type of project -- assigning
highly qualified personnel with appropriate tools and authority to make such
reviews, and assuring that they interact with project managers in a way that
allows them to recognize issues as they arise. These reviews should also include
financial- capacity assessments, as well as engineering reviews. It is also most
important that top management be informed, on a regular basis of the status of
Megaprojects and be given sufficient information to act when changes are
necessary. Issues in Project Oversight: The remainder of my testimony will focus
on a number of current issues in project oversight and project management. They
fall under three headings: fraud protection, project cost control, and quality
assurance, Fraud Protection: AASHTO and its member state DOTs are absolutely
committed to eliminating fraud in the federal highway program. We are committed
to working with the Federal Highway Administration, the US DOT Inspector General
and the US Department of Justice in identifying and prosecuting instances of
fraud. While we do not believe that costs associated with fraud are large, the
instances of fraud undermine the whole program and bring into question the
credibility of everyone involved. While zero tolerance is our goal, we must also
be mindful of the costs of additional oversight and controls, especially if it
adds significantly to project delivery time. So we will work with FHWA to
achieve a balanced approach. One example is the increased attention to the
Megaprojects, since the larger the project, the more opportunity for fraud.
Project Cost Control: This issue involves both cost estimating and cost growth.
In line with current planning requirements, cost estimates are made at the
earliest stages of project development, and thus are only the most basic
estimate of what costs may be. However, this early cost estimate gets a lot of
publicity, as it is used to gain initial project approval. As the project
progresses thorough design stages, more detail such as design alternatives and
environmental considerations --becomes clearer and engineering cost estimates
evolve and change. At the completion of the final design stage, plan
specifications and estimates are fully developed and an "engineer's estimate" is
prepared. This final "engineer's estimate" is used by FHWA to program the
funding for the project. The project then goes to bid, and often addendums are
issued to take care of design oversights discovered during the bid period. Then,
a contract is executed based on the lowest acceptable bid. Virtually every
project has change orders during construction, which usually result in a higher
final project cost. A key issue in evaluating how much the project increased, in
cost is the benchmark used. Do you use the pre-design planning estimate, the
engineers estimate, the low bid, or some other benchmark? A major contributing
factor in cost growth is time. It can take as long as 10 years for a project to
make it through the planning, environmental and project-development process.
This time factor will naturally lead to substantial changes in cost estimates.
Streamlining the project-development process is essential to cost control.
Project reviews during the pre-design and design phase need to be done
concurrently, not sequentially. Also, costs are often compared to the initial
estimate, creating the impression of dramatic cost swings in the project. Most
of the cost growth from the early planning stages to start of construction is
related to inflation and scope changes brought about by the public involvement
and environmental mitigation requirements. A key issue in evaluating how much
the project increased in, cost is the benchmark used. Do you use the pre-design
planning estimate, the engineers estimate, the low bid, or some other benchmark?
The Project Oversight Task Force is looking at ways to refine this estimating
process, and will offer recommendations on how that might be accomplished. By
way of example, we could much more clearly explain the estimates, and we want to
work closely with FHWA to clarify the stages of project development.
Construction cost control is also a critical part of project oversight and
management. In that regard, AASHTO's Standing Committee on Highways--whose
members are the Chief Engineers of State DOTs--conducted a survey of
construction cost-growth. The survey, conducted last September, examined data
from projects completed between January 2000 and May 2001. This sample included
over 400 projects valued at $
9.2 billion. The results showed
that final cost vs. the engineer's cost estimate made prior to bids varied by an
average of 3.3 percent. Further when comparing final costs to the contract bid
prices, these projects experienced an average 11 percent change. This data
clearly supports that conclusion that the largest share of cost variance occurs
in the pre-construction phase of projects. Consequently we need to refine this
part of the process to ensure the best estimates are made and understood. We are
also examining the reasons for cost growth during construction and actions to
take to control those costs. There is some project costs that are extremely
difficult to estimate at the early stages, and may even be incurred after the
end of construction. Specifically, environmental mitigation and the acquisition
of right-of-way vary on a project-by-project basis and is frequently the subject
of litigation, which can delay a project and add inflationary costs. Our Project
Oversight Task Force will thus concentrate on design and construction costs.
Quality Control: While cost is a significant factor in project management,
quality control is of equal importance. Clearly, sacrificing quality simply to
reduce the cost of a project is not the appropriate answer. . For the past 10
years, AASHTO has worked cooperatively with FHWA and our industry partners to
help ensure that quality is our first priority in the construction of
transportation projects. This has been conducted through the
National Partnership for Highway Quality. Over the past decade, this partnership
has advocated such items as increased public interaction and involvement,
development of formal quality assurance and quality control plans (including
specific methods to measure quality results), and the use of innovative
approaches to add value to a given project - called Value Engineering. Down the
road, these approaches lead to new design standards and construction
specifications that improve the overall quality of our
transportation system. Often, these new approaches and
increased attention to detail increase the initial cost of a project. New
approaches add benefits in the long run that can lead to decreased maintenance
costs, less- frequent reconstruction, and reduced disruption to the traveling
public. These long-term payoffs more than compensate for the initial increases
in construction costs. We are also working with the States to increase the
number of value engineering change proposals during construction. These changes
suggested by the contractor result in cost savings with the saving shared with
the contractor. Another area that we are turning to is the move to
"performance-based" specifications for
transportation projects.
Instead of specifying particular construction materials and techniques, the
State DOTs are experimenting with specifying the "outcomes" that a project
should attain, such as certain levels of ride smoothness and the minimization of
life-cycle costs. These performance-based outcomes lead to better-quality
projects, but can also increase the initial project costs. State DOTs also are
experimenting with quality incentives. This concept includes paying contractors
to produce a higher level of quality on a project, such that the long-term
benefits to the traveling public will outweigh the payment made. Incentives are
also paid on certain projects for early completion of construction, which may
increase the initial cost of a project, but which ultimately saves the taxpayers
money by opening a facility sooner, thus reducing congestion and the time and
money that is lost in traffic jams. Another major effort at quality control is
AASHTO Materials Reference Lab (AMRL). The AMRL staff inspects and accredits
laboratories to insure the quality of construction materials (aggregate,
bituminous materials, cement & concrete). AMRL has accredited approximately
700 labs nationwide. Human Resources and Technical Resources: It is clear that
the best systems are no substitute for well trained and experienced personnel.
They are the linchpin of any system of project oversight. We are clearly
experiencing the loss of some of our most experienced personnel to retirement
and to the private sector. Personnel reductions at all levels of government
contribute to this loss. I am not suggesting that we should add personnel in
wholesale fashion. However, we need to assess the skills needed by our personnel
to meet today's needs, and work to ensure that we appropriately add personnel
who will represent the next generation of leaders in this field. To that end,
AASHTO is working to promote interest in careers in the
transportation field and is promoting the development of
technical training to ensure we have the appropriate skills to meet the complex
needs of today and tomorrow. Our personnel also need modern systems for project
management. Many of our systems that were state-of-the- art have been overtaken
by the extraordinary advances in technology. We need to help to provide the
financial resources to upgrade these systems and to train personnel in their
effective use. AASHTO supports increased resources authorized for training and
development of project management tools, such as BAMS. Conclusions In
conclusion, I would like to state that AASHTO and its members have always placed
a premium on assuring that projects receive appropriate oversight and that our
techniques and systems for estimating costs are well-maintained and updated. We
have experienced an evolution in the project-management process, and we plan to
utilize the wealth of experience we have gained over the years to assure an
effective process. This will include the dissemination of best practices, the
refinement and updating of software products used for project management and
fraud detection, and to assure that well-trained personnel are in place to carry
out our responsibilities. The Federal-aid Highway Program has been a major
success and we look forward to assuring its continued growth and success in the
future.
LOAD-DATE: May 6, 2002